Waka Kotahi NZ Transport Agency is continuing to monitor progress on Transmission Gully as the contractor, Wellington Gateway Partnership (WGP), and their sub-contractor, CPB HEB Joint Venture, work to complete construction of the motorway and meet the required safety, quality and environmental tests.
Construction on Transmission Gully is inching closer to the finish line, but the contractor, Wellington Gateway Partnership (WGP), and their sub-contractor, CPB HEB Joint Venture, still have more work to do before the road can open.
Under the PPP contract, it is the responsibility of the contractor, Wellington Gateway Partnership (WGP) and their sub-contractor, CPB HEB, to deliver a road that meets…
Waka Kotahi NZ Transport Agency is advising motorists to plan ahead for significant delays between Porirua and Tawa on Saturday 6 and Saturday 13 November, as Transmission Gully crews finish laying 1000 tonnes of asphalt along a 900m stretch of road connecting the southern end of the new motorway with the existing State Highway 1.
Waka Kotahi NZ Transport Agency is advising motorists to plan ahead for closures of State Highway 1 at Mackays Crossing over four nights starting this Sunday 3 October 2021.
Motorists travelling overnight on State Highway 1 (SH1) between Tawa and Porirua will need to take a detour route for up to three nights next week, while a signage gantry is installed across the width of SH1 for the new Transmission Gully motorway.
Waka Kotahi NZ Transport Agency is working with the Transmission Gully Public Private Partnership contractor, Wellington Gateway Partnership (WGP), and its subcontractor, CPB HEB Joint Venture, to confirm a new opening date for the motorway.
State highway works in Wellington and Wairarapa are resuming, following the move to COVID-19 Alert Level 3 this week for most of New Zealand, excluding Auckland and Northland.
Waka Kotahi NZ Transport Agency is advising that work will continue on Wellington and Wairarapa state highways to ensure the roads remain safe for essential workers, for the movement of essential goods and to support lifeline functions during the Covid-19 Alert Level 4 lockdown.
With less than three months until the contractually agreed opening date of 27 September 2021, Waka Kotahi NZ Transport Agency says the Wellington Gateway Partnership (WGP) contracted to build, operate and maintain the Transmission Gully motorway, and its design and build subcontractor the CPB HEB Joint Venture are continuing to advise Waka Kotahi that they remain confident of meeting their contractual commitments and opening the road on time.