Scam alerts: we’ve seen an increase in scam texts and emails claiming to be from us, asking for payments. Check our example scams or report a scam to us
NZTA App:our mobile app provides a simple and secure way to access your driver licence and vehicle information. Learn more and download the NZTA app
Waka Kotahi is pleased to report smooth and reliable journeys throughout the wider Wellington transport network on the second day of operation for Transmission Gully, Te Aranui o Te Rangihaeata.
Waka Kotahi is reporting a noticeable reduction in congestion and improved journeys across the wider Wellington transport network after the first full day of operation for Transmission Gully, Te Aranui o Te Rangihaeata.
The long wait is nearly over for Wellingtonians, with Transmission Gully set to open to traffic within 24 hours following this morning’s ribbon cutting ceremony at the northern end of the newest portion of SH1.
Waka Kotahi NZ Transport Agency says the completion of a huge amount of work on the Transmission Gully motorway over summer has brought the road to a stage where Waka Kotahi is confident that it is safe for public use, and it has instructed the contractor to open the road to traffic before the end of this month.
CPB HEB, the company subcontracted to build Transmission Gully, has now had 67 of the 81 remaining safety and quality assurance tests required before the road can open accepted as meeting the required standards.
Many of the remaining safety and quality assurance tests required under the Public Private Partnership (PPP) contract to allow Transmission Gully to open are close to being finished.
Waka Kotahi NZ Transport Agency says the builder of Transmission Gully CPB HEB is continuing to make good progress fixing construction defects and pavement issues required for the Transmission Gully motorway to open.
Waka Kotahi NZ Transport Agency says recent on-site investigations by Waka Kotahi roading experts shows significant progress has been made by the builder, CPB HEB, towards fixing construction defects and pavement issues required for the Transmission Gully motorway to open.
One additional safety and quality assurance test was met last week by CPB HEB, the builder of Transmission Gully. Some of the outstanding tests require remedial work before they can be met, including the road surface and pavement and construction defects.
An additional two safety and quality assurance tests were met last week by CPB HEB, the builder of Transmission Gully, while work continued onsite on pavement remediation and the stormwater system.
Waka Kotahi NZ Transport Agency says no further progress has been made since the previous weekly report in completing the required safety and quality assurance tests needed for Transmission Gully to open to traffic.
Waka Kotahi NZ Transport Agency is continuing to work with the Transmission Gully contractor Wellington Gateway Partnership (WGP) and their subcontractors, CPB HEB Joint Venture and Ventia, to support getting the new motorway open to the public as quickly as possible.
Waka Kotahi NZ Transport Agency says Wellington Gateway Partnership (WGP) and CPB HEB Joint Venture, the builder contracted to deliver the Transmission Gully project, have run out of time to complete all of the tasks necessary for the road to open in time for Christmas.
Waka Kotahi NZ Transport Agency’s latest update on Transmission Gully shows that the contractor, Wellington Gateway Partnership (WGP), and their sub-contractor, CPB HEB Joint Venture, still have a lot of work to do before the road can open.