Opportunity charging is when battery electric buses are charged while out of the depot with the charger generally being located at bus stops or layovers. Opportunity charging is often time constrained because the charging window is the length of a dwell at a bus stop or a layover (typically between 30 seconds and up to 30 minutes in duration). Therefore, opportunity charging normally uses DC chargers which are able to transmit a large amount of power over a short time period.

Typically, opportunity charging tops up the batteries in order to extend the range of battery electric buses but does not fully charge the electric bus batteries. The additional range provided by opportunity charging depends on its duration and the power rating of the charger.

The table below shows the additional range provided by different types of opportunity chargers assuming that a battery electric bus consumes 1.5 kWh per km (electric bus manufacturer specifications gave a range of efficiencies between 1.2 kWh/km and 1.9 kWh/km with heavier buses generally having higher energy use).

Table: Additional range provided by different types of opportunity chargers assuming bus consumes 1.5 kWh/km

Charger power rating

1 min charge (dwell at bus stop)

10 min charge (duration of layover)

150 kW

1.7 km

16.7 km

300 kW

3.3 km

33.3 km

600 kW

6.7 km

66.7 km

The cost of purchasing and installing an opportunity charger generally increases with the power rating therefore opportunity chargers are sized to provide the additional range required before the next charge.  To reduce the demand on the electricity grid some opportunity chargers have built-in energy storage such as capacitors or batteries.  This built-in energy storage allows the opportunity charger to be charged gradually from the electricity grid and then rapidly release the energy to charge the bus.

Not all battery electric buses are compatible with opportunity charging and bus manufacturers may specify a limit for the maximum charging rate that can be used. Therefore, bus operators and public transport contracting authorities should determine whether opportunity charging is required and their requirements for the charging rate before procuring battery electric bus fleet.

The overall advantages and disadvantages of using opportunity charging instead of relying solely on depot charging are discussed in the table below:

Table: Advantages and disadvantages of opportunity charging

Advantages

Disadvantages

  • Extended vehicle range which can avoid the need for additional buses and drivers
  • Spreads the electricity demand across multiple locations which may avoid the need for a primary substation upgrade
  • May lower the weight of the vehicle because less battery capacity is required which could enable more passengers to be carried
  • Capital cost from purchasing and installing the opportunity chargers, especially high powered fast chargers
  • Potentially reduced battery life compared to depot charging only
  • Risk of operational issues if charger is out of order or occupied
  • Reduced interoperability of buses in situations where only some routes have opportunity chargers installed

Current practice is for the capital cost of opportunity charges to be negotiated between the public transport contracting authority and the bus operator on a contract-by-contract basis.  However, this is an evolving area of practice which may change as opportunity chargers become more common in New Zealand.

Types of charger connections

There are three main types of connections between the bus and the charger: plug-in, pantograph, and induction: 

  • Plug-in uses a cable to connect the bus to the charger.
  • Pantograph uses an extendable connector which is either located on the bus or on the charger. 
  • Induction chargers use a primary coil built into the road surface and a secondary coil located on the underside of the bus. During charging, an electrical current is passed through the primary coil to create a magnetic field, inducing an electrical current in the secondary coil which charges the bus battery.  

The advantages and disadvantages of the charger connection types are shown in the table below:

Plug-in

A charger plugged into a bus

Plug-in charging at Wellington airport. (Source: Lorelei Schmitt)

Advantages

Disadvantages

  • Lower cost to purchase and install the charger
  • Lower energy loss because a physical connection is made
  • Manual process to connect the bus to the charger
  • Can be affected by human error, requires manual operation, and prone to wear, damage and trip and fall
  • Cables can be awkward to move around depending on their weight

Pantograph

A pantograph connected to a bus at a bus stop

Pantograph charging. (Source: Lorelei Schmitt)

Advantages

Disadvantages

  • Quick to make a connection which is an automated process
  • Lower energy loss because a physical connection is made
  • Requires an overhead structure
  • Higher infrastructure costs
  • Depending on location can be difficult to gain permission to install

Induction

Conceptual diagram of induction charging through  a wireless ground pad

Induction charging. (Source: Auckland Transport)

Advantages

Disadvantages

  • Improved aesthetics because no overhead structures or cables are required
  • Quick to make a connection which is an automated process
  • Higher energy loss during transmission
  • Requires the charging plates to be built into the road
  • High cost

For opportunity charging the speed of the connection is important, therefore, pantograph or induction are typically used, whereas for depot charging efficiency is important therefore plug in or pantograph are often used. Increasingly, technology is evolving to support chargers that are faster to connect and more efficient at charging. Depending on the manufacturer some battery electric buses can use multiple connection types (eg plug in and pantograph) while others have only one connection type.

Top down vs bottom up pantographs

The two types of pantograph charging systems are:

  • Bottom-up (also referred to as roof mounted pantograph)
  • Top-down (also known as inverted pantograph)
Diagram of pantograph charging either bottom up or top down

Pantograph (a) bottom-up and (b) top-down.

There are advantages and disadvantages to each type of pantograph and varied industry preferences for one or the other in New Zealand. Australia uses top down. Which is preferable is largely dependent on operational needs. Ensure whichever you choose, if you will be using pantographs at all, is compatible with your operational requirements such as the CCS2 plug type and the number of buses you would like to be charging at any given time.

Note that top-down pantographs have less equipment on the bus and more equipment on the overhead structure, this means less weight for the bus to carry but also means that the overhead structure must be stronger and bulkier. For bottom-up pantographs, the pantograph arm and electrical equipment is generally made lighter because this is carried by the bus and with less equipment on the overhead structure this can also be made lighter.

With bottom up, configuration failure of the charger mechanism requires the bus to be taken out of operation, whereas for top-down configuration the failure of the charger mechanism can impact on wider service delivery. Australia’s preference for top-down pantograph charging relates to a perception that it is more reliable than bottom-up and has lower maintenance costs, though these are still typically higher than plug-in charging maintenance costs.

A top-down pantograph lowers from the overhead charger and connects to the bus whereas a bottom-up pantograph raises from the bus and connects to the overhead charger.

Pantograph types (a) top-down and (b) bottom-up. (source: ABB)

The typical characteristics of each type of pantograph are listed in the table below. 

Table: Typical characteristics of each type of pantograph
(Source: Pirooz, A., Heidari Gandoman, F., Firouz, Y., & Van Mierlo, J. (2020). Feasibility study of reconfigurability between different power transmission concepts for electric bus charging. In Transport Research Arena)

Parameters

Top-down

Bottom-up

Unit

Maximum rated voltage

1500

1000

VDC

Nominal voltage

750

750

VDC

Charging current

500

500

A

Maximum current (<10min)

600

800

A

Electric lowering unit voltage

24 ± 30%

24 ± 30%

VDC

Contact force

500

250 +10%

N

Total weight

175~180

85

Kg

Operational temperature

-30 to +65

-30 to +65

°C

Case study: Wellington Route 1

In 2019 bus operator Tranzurban implemented 10 battery electric double deck buses in Wellington. These buses are used on route 1 (Island Bay to Churton Park/ Johnsonville West/ Grenada North) which is a 21km long route that has frequent services and gradients of up to 8%.

Each bus can carry up to 90 passengers and has a range of 150km on a single full charge. To extend the range the buses use a 450kW bottom-up pantograph charger at the Island Bay terminus to charge for 10 minutes during the layover and driver breaks.

A bottom-up pantograph charger connected to double deck bus in Wellington at a bus stop.

Battery electric double deck bus with pantograph opportunity charger. (Source: Lorelei Schmitt)

Lessons learnt:

  • This type of opportunity charging is a viable way to augment battery charging, making efficient use of layover time and enabling smaller battery packs on the buses which can reduce bus costs and weight
  • The on-route high speed charging enabled several buses to be charged using just one charger and a small transformer compared to a depot-based strategy. More specifically, a single 450kW charge running off a 500KVA transformer was used rather than a depot-only based charging strategy which might use a 1.5-6MVA to charge a depot of buses with large batteries in a 7-hour overnight charge window (10pm-5am).
  • The smaller battery packs enabled by this type of opportunity charging may still require a charge at the depot overnight but the demand on the electrical infrastructure supply would be less
  • Being on public land made the consenting process a bit complex; it required a wrap of the charging infrastructure, harmonics testing and numerous visual designs to be submitted.
  • The time available to undertake top up charging was somewhat limited in this location by the timetable. In this type of charging strategy, timetables must be structured to be sympathetic to the need to charge.
  • This type of charging strategy is more appropriate for locations that serve as the terminus to high frequency services and/or have additional routes terminating nearby.
  • Ongoing maintenance is an important consideration: this pantograph is located near the ocean in a windy part of Wellington and thus the mast connection plate has been subject to salty sea spray which has required cleaning of the hood to take place approximately every three months or after a significant storm. This takes approximately half a day.
  • Some drivers have struggled to line the bus up for connecting the pantograph. That said, visual aides to support accurate bus alignment have been in place for more than 3 years, which has enabled near 100% strike rate.
  • Another option for opportunity charging in this location would now be a street side pedestal with a charging lead, though this technology may have been less viable at the time this project was established.