Māngere is a large suburb located near Auckland Airport. The area is multicultural with large Pasifika, Asian, Māori, and European communities living in the suburb.
Like most Auckland suburbs, Māngere has historically seen more road capacity developed to meet the demands of increasing motor vehicle traffic and active travel infrastructure has been of relatively lower priority. The suburb is dissected by two motorways (SH20 and SH20A) as well as several busy arterial roads.
Completed in 2017, ‘Te Ara Mua – Future Streets(external link)’ was a flagship project in Central Māngere (see project area map below) that involved changing the features of Māngere streets in order to:
A key feature of the design process was community participation to understand local concerns and aspirations. The Local Board and a community reference group had a leadership role in the community engagement process and many meetings, conversations and events with various groups were held. A stall set up in the local shopping mall, with maps and opportunities for people to plot their normal trips and the issues experienced on them, was particularly successful. All together 43 formal community engagement sessions were carried out, in addition to numerous informal meetings of various kinds. A rich explanation of how travelling around Māngere was experienced by local people was achieved. The specific locations of problem areas were identified, as were key issues that had high levels of agreement.
These were:
All of the issues and opportunities were then combined with other city-wide aspirations (such as healthy communities, safer streets and a better cycle network) and background theory (self-explaining roads), to create design objectives for the street interventions.
A design committee, including representatives from the research team, Auckland Transport and other consultants, debated and developed the design concepts, in conjunction with the community reference group over a total of seven participatory planning sessions (three with the community reference group and four with the design committee). In between these meetings, design work was carried out by sub-groups taking direction from the design committee.
The introduction of high-quality cycling infrastructure was one aspect of the design approach that was not overtly raised by the community through the engagement process, although concerns about cycling safety on the road were raised. Improving cycling facilities was introduced by the design team, in response to emerging leading practices, a national desire to see better quality cycling routes, the development in cycling infrastructure in other parts of the city and a generally future-focussed approach. There were also some local champions for better cycling infrastructure.
The works included:
Reference: Te Ara Mua - Future Streets suburban street retrofit(external link)
Project owner: Auckland Transport
There were a number of challenges that were overcome in the design phase of Te Ara Mua, and then enablers that eventually allowed the project to proceed, including:
Reference: Te Ara Mua Future Streets: The process of implementation and short term lessons(external link)
Close
Despite its challenges, Te Ara Mua was overall regarded as a success. The key components that made it successful include:
Key learnings include the need to ensure: