Published: 8 April 2022 | Category: Technical advice note | Audiences: Road controlling authorities, Road traffic engineers & consultants, Roading contractors
This note is to advise of interim updates to the Waka Kotahi NZ Transport Agency State Highway Construction Contract Proforma Manual (SM031). Updated documents have been released to be used for all future procurement and are available for download from the Waka Kotahi website.
This note is to advise of interim updates to the Waka Kotahi NZ Transport Agency State Highway Construction Contract Proforma Manual (SM031). Updated documents have been released to be used for all future procurement and are available for download from the Waka Kotahi website.
The updates apply from the date of this notice.
The State Highway Construction Contract Proforma Manual (SM031) is utilised by Waka Kotahi and external consultants when preparing state highway tender documents for traditional, design and construct, lump sum, alliancing and minor works and physical works construction contracts.
The processes and procedures outlined in this update must be followed by Waka Kotahi for all physical works construction contracts that are undertaken from now on.
In light of the change to the COVID-19 Protection Framework and further changes to reflect the spread of Omicron in New Zealand, Waka Kotahi has reviewed and updated the Communicable Disease clause in the SM031 Manual to reflect the current environment and to ensure Waka Kotahi continues to take a consistent approach with any future COVID-19 claims (and other similar events).
The changes to SM031 include:
The changes can be found at:
State Highway Construction Contract Proforma Manual (SM031)
Our target audience for this manual is generally internal staff and those external consultants who conduct procurement on behalf of Waka Kotahi. As a result, our communications will mostly be focussed internally. Advice of these changes will be promulgated by:
The SM031 Manual is published for use on the Waka Kotahi website and InfoHub and will be updated to reflect the changes.
A review of the effectiveness of the current SM031 Manual will occur in 2022.
Author: Waka Kotahi NZ Transport Agency
Published: March 2022
Version: 1
Location: State Highway Construction Contract Proforma Manual (SM031)
If you have any questions or feedback, please contact the Senior Procurement Advisor – Procurement Excellence at procurement@nzta.govt.nz using the subject line ‘Feedback for SM031’.
Signed:
Greg Haldane
Chair, Ratification Group
Vanessa Browne
Delegated Approver