Project Introduction

This project will improve safety at Bombay Interchange by installing traffic lights on the southbound off-ramp, the northbound off and on-ramp and the nearby exit of the Bombay service centre on Mill Road.

  • Estimated project dates

    Aug 2024–Feb 2025
  • Estimated project cost

    $3 million
  • Project type

    Safety improvements
  • Project status

    Construction

Project updates

Progress update

The installation of traffic lights at Bombay Interchange and the Bombay service centre exit got underway in September 2024 and  is expected to be completed in late February 2025.

Works will be staged to minimise disruption, with the activities likely to have the greatest impact on traffic flows being undertaken at night.

View the latest updates:

To receive these monthly progress updates via email, please subscribe using the link below:

Project background

Following early engagement with the Franklin Local Board on the SH1 Papakura to Bombay project, the NZ Transport Agency Waka Kotahi (NZTA) investigated concerns raised over safety, congestion and access at Bombay Interchange.

Investigations and modelling by NZTA determined that the most appropriate short-term solution to improve safety and reduce congestion is to install traffic lights at the Bombay Interchange and the adjacent BP Bombay service centre exit on Mill Road.

The future plans for upgrading Bombay Interchange are part of Stage 2 of the Papakura to Bombay project. View the design plans:

Design plans for Stage 2 of the wider Papakura to Bombay project [PDF, 13 MB]

  • scroll to the far right end of the plan.

The earlier investigations and work undertaken on this project are summarised below.

  • Summary of investigations and work undertaken
    • In late 2019/early 2020, the Franklin Local Board raised concerns with the SH1 Papakura to Bombay project team on behalf of the community over safety and congestion at Bombay Interchange, particularly when using the southbound off-ramp.
    • In 2020, NZTA commissioned a traffic analysis of the interchange and in early 2021 those investigations were undertaken and reported back.
    • In July 2021, the report and recommendations were presented to the Franklin Local Board. The report recommended that the southbound and northbound off-ramps and the northbound on-ramp at Bombay Interchange should have traffic lights installed.
    • In August 2021, at the request of the Franklin Local Board, NZTA began discussions with bp NZ due to similar issues experienced at the exit of the bp Bombay service centre at 216 Mill Road, immediately beside Bombay Interchange.
    • In late 2021, further investigations and modelling were undertaken, including the interchange ramps and the Bombay service centre exit.
    • In early 2022, nine different options for improvements at the interchange and adjacent service centre exit were modelled – all included benefits and drawbacks.
    • In the short-term none of the options modelled would be able to resolve all the congestion issues at the interchange and service centre exit.
    • However, signalising the interchange and the service centre exit with traffic lights right now will provide immediate and significant safety benefits for motorists using the interchange and visiting the Bombay service centre.
    • A review was undertaken of the two short-listed options and the preferred option was progressed through to preliminary design and costing.
    • Since March 2022, regular updates have been reported back to the Franklin Local Board and Bombay community groups.
    • Topographical surveys, underground service plans and a draft concept design were completed by the end of 2022.
    • A preliminary design review, road safety audit and cost estimates of the selected option were completed by mid-2023.
    • Construction funding for the signalisation project was approved by NZTA in October 2023, and agreement was reached on a financial contribution from bp NZ towards signalising the adjacent Bombay motorway service centre exit.
    • Construction cost estimates were completed in early December and detailed design was completed by Christmas 2023.
    • Procurement was undertaken in early 2024 to appoint a construction contractor and the contract was awarded in late July 2024.
    Close