SH2 traffic notice for ongoing works on SH2
Well maintained roads are an important part of keeping people safe. While we aim to do this work with as little disruption as possible, we know that roadworks can be inconvenient. Thanks for your patience while we do these important works.
Please drive carefully through work sites and stick to the temporary speed limits.
Intended programme for 2024
Our programme is weather dependent, so may be postponed to the next suitable day/night.
Location |
Type of work |
Schedule |
SH2/Sharp Road Intersection
|
Roundabout construction underway with significant activities. Night works stop/go for asphalt works. There will also be daytime intermittent stop/go traffic management in place which may cause longer delays, but typically expect minor delays of one to two minutes. |
Ongoing to mid-2024
|
SH2/Apata Station Road
|
Road widening works underway, these are enabling works for roundabout construction. Contraflow in place with speed restrictions. There will be intermittent stop/go traffic management in place which may cause longer delays, but typically expect minor delays. |
Enabling works for roundabout site estimated completion 2025
|
SH2/Ōmokoroa Road |
Shoulder closures in place with speed reduction for early works. |
In progress |