• 1 Apr 2022

Sit back and take a flight across the Takitimu North Link project site in Tauranga, flying from Smiths Farm to Te Rangituanehu / Minden – it’s a great view of progress to date with commentary from Environmental Manager Stephanie Kirk.

While a lot of the work to date hasn’t been that visible to the public, contractors Fulton Hogan and HEB Joint Venture have been flat out moving about 50,000m³ of dirt for earthworks, clearing vegetation, undertaking archaeology investigations and service relocations - as well as significant environmental work.