• 26 Aug 2024

Take a look at the latest flight over the Takitimu North Link Stage 1 project site in Tauranga, with commentary with Dillion, our Environmental Graduate.

The project continues to carve impressively through the landscape, with three bridges complete and 1,200,000 earthworks achieved. As planning for the next construction season is underway, it’s a good chance to reflect on the significant progress to date on the 6.8km 4-lane expressway. From spring 2024, the focus shifts to major works at Fifteenth Ave, State Highway 29, and Minden Road, Te Puna key sites.