SH1 Picton elevation repairs

Section menu

Project introduction

Work to repair the slow vehicle lane on State Highway 1 at the Picton Elevation to stop future ground movement and build resilience is largely complete with all three lanes open. A temporary speed limit of 70km/h will be in place until chipseal can be applied when the weather is warmer.

  • Estimated project dates

    Nov 2023–Jun 2024
  • Project type

    Road improvements, Road maintenance
  • Project status

    Construction, Investigation

About the project

Following the most recent movement of the slow vehicle lane on State Highway 1 at the Picton Elevation in early 2023, investigation, monitoring and design work was undertaken to determine the best way to repair this stretch of the state highway.

Investigation and monitoring revealed the groundwater flow was under pressure and had pushed through the state highway. This caused upward pressure just below the surface of the slow vehicle lane, cracking the road’s surface

In early January 2024 horizontal drains were installed to slowly drain the pressurised water under the highway. Additional culverts were then installed, with associated inlet and outlet protection, along with under road cut off drains to improve slope stability by controlling groundwater pressures through subsurface drainage. Following this work the team was able to make repairs to the road surface of all three lanes.

On 8 June all three lanes reopened. To ensure the safety of all road users a temporary speed limit of 70km/h will remain in place until a layer of chipseal can be applied when the weather is warmer.

Due to the complexity of this site, we will continue to monitor this section of State Highway 1.

  • Key features

    Drainage works as part of this project have been funded from the Transport Resilience Fund announced in 2023. Road repair works have been funded from the Emergency Works Fund.

    Close
  • Project timeline
    Stage Action Status
    Stage 1 Preparation for directional drilling. This includes:
    • Removal of a section of guardrail
    • Removal of vegetation
    • Excavator onsite
    Complete
    Stage 2 Installation of directionally drilled drains.

    The excavator will be onsite to reach into the creek and directionally drill pipes back under the road.
    Complete
    Stage 3 Installation of new culverts.

    Installation of new sumps and drainage channels on the eastern side of the state highway.

    Installation of new outlets and bank protection on the western side of the state highway.

    Slumped pavement repair in the western slow vehicle lane.
    Complete
    Stage 4 Road reopens to three lanes under a 70km/h temporary speed limit Complete
    Stage 5 Chipseal applied to three lanes and 100km/h speed limit reinstated September/October 2024
    Close

Our partners on this project