Project introduction

State Highway 2 over the Remutaka Hill road closes for its annual maintenance and slip prevention work on various nights between January and November 2024. The schedule is available on this page. The highway may have to close at other times for emergency works, weather or accidents.

  • Estimated project dates

    Jan 2024–Dec 2024
  • Project type

    Road maintenance

Subscribe to updates

What does subscribing mean? Please read our Privacy statement

 

Remutaka Hill closures until June 2025

Number of nights closed

Start 9pm

Finish 4am

5

23 February

28 February

1

9 March

10 March

5

6 April

11 April

1

18 May

19 May

1

15 June

16 June

Book your escorted crossing here.(external link)

Urgent Remutaka Hill closures finished

Crews have completed the majority of the underslip repair works ahead of schedule and further night-time road closures are no longer required.

Road users can now travel SH2 Remutaka Hill road at night without making an escorted crossing booking.

Some additional works are still required to complete the underslip repairs, but these can be completed with stop/go traffic controls in place. A 24/7 stop/go will remain in place at the underslip site until further notice.

We thank everyone for their patience and understanding during these night road closures.

Underslip progress updates

Pile installation and foundation works at the underslip site on State Highway 2 Remutaka Hill have continued this week. The piles and foundation are critical elements for the retaining wall, which will restore the road and protect it from further damage.

We have completed installation of 12 out of 15 piles. We expect to complete the final three pile installations next week and begin timber construction for the retaining wall. Rock anchor testing has been completed to ensure the next phase of work remains on track.

Crews will also be busy during the day next week, as they start installing rock anchors to provide extra reinforcement to the hillside.

Our crews have also been completing routine maintenance to make the most of the night-time closures. This has included road resurfacing, line marking, drainage renewals, channel clearing and barrier and sign installations. This helps us get ahead on next year's maintenance schedule.

Why close the road?

The SH2 Remutaka Hill road is the main artery linking the Wellington and Wairarapa regions, with an average of 7,219 vehicles using the road daily.

Of these, around 256 use the road between 9pm and 4am. With the nearest detour route over 100km away, effective maintenance of the road is critical for both the Wellington and Wairarapa communities.

The safest and most efficient way to maintain the road, is to close it. This avoids more frequent disruptions and helps keep our crews safe.

Following consultation in 2019, we found the best way to carry out maintenance work was to do block closures and we will continue to do this in the future to keep the road safe.

  • Detour route

    The only detour is via State Highways 1, 57 and 3. As this is very long detour, we advise vehicles to travel early if possible or book an escorted crossing. There will be detour signs in place during this time.

    Travelling from the Hawkes Bay?

    Vehicles travelling from the Hawkes Bay region needing to head south of the Remutaka Hill should detour at Woodville and travel via Ashurst to get to State Highways 3, 57 and 1.

    Close

What roadworks are completed during closures?

There is a lot of work that takes place during the Remutaka Hill road closures. Taking full advantage of the road closure, we schedule as much work as possible to avoid other disruptions while the road is open.

  • Slip prevention works

    Rockfall protection work is carried out to protect the road from slips which can cause major disruption. This work involves clearing vegetation and loose rocks and then installing netting which is designed to catch loose material as it falls.

    Close
  • Maintenance works

    Maintenance work we complete on the hill is one of the most important things we do to keep the hill safe. We schedule as much maintenance work as possible during each closure. At any time during the closure there could be up to 100 crew members doing a variety of activities. This includes:

    • asphalt resurfacing
    • fixing potholes
    • road marking
    • mowing and landscaping
    • road inspections
    • drainage inspections
    • guardrail repair works
    • signage maintenance
    • edge marker post maintenance
    • sump clearance
    • road sweeping (includes litter collection, channel clearance etc).
    Close
  • Safety improvement works

    New side barriers at high-risk locations, along the Remutaka Hill will be installed. Also more motorcycle under-barriers will be installed, to improve safety for motorcyclists. The improvements include improved road signage and road markings too.

    Close

Videos

July 2024

Learn more about the importance of regular SH2 Remutaka Hill road maintenance night closures.

Crew operating a milling machine along the Remutaka Hill.

Crew installing an under barrier which are designed to protect motorcyclists if they crash.