This Road of Regional Significance project improves SH6 and SH6A, Joe O’Connell Drive and Hansen Road intersections to support an efficient and reliable transport network to address growth in Queenstown.
Sign up for the Kā Huanui a Tāhuna newsletter(external link)
Work notices outline the days, time and duration of specific pieces of work that may cause disruption.
We all know that the State Highway 6/6A intersection in Frankton (BP roundabout) is at capacity at peak travel times, and something needs to be done to make it easier for people to drive, walk, cycle, and for buses to move around the area.
We have prioritised construction of the works in Frankton which include installing traffic signals at the SH6 and SH6A Frankton intersection, the adjacent SH6/Hansen Road link intersection and the SH6 Joe O’Connell Drive intersection. We’ll extend the Bus Hub and add traffic signals at the entry and exit to make that movement easier for buses. We will also be constructing new bus stops, adding cycle lanes, and creating shared use paths.
In April 2024 we began a significant programme of work to remove, shift and improve services and utilities that were located under the future road layout at the intersection of SH6 and 6A. So far we have laid 5.7km of lower voltage cable, 3.66km of gas and other ducting and 740m of 1.4 diameter pipes to help Queenstown cope better with its growing population in the future. Put together, these services make up about 100 individual pipes and ducts crossing SH6, in 32 individual trenches, with between one and 10 service lines in each.
All road closures have been at night to minimise disruption to the state highways.
Undergrounding power and upgrading the stormwater underneath the Gray and McBride Street intersection has been completed and most of Gray Street has been rebuilt, including new footpaths. The SH6 end of Gray Street won’t be finished completely due to the work to double the size of the Bus Hub, which began in early 2025. However, finishing most of the work in this area means there is less impact on Frankton Village.
The works are being delivered for Waka Kotahi as a Road of Regional Significance project via the Kā Huanui a Tāhuna Alliance in partnership with Queenstown Lakes District Council.
CloseThere is a significant amount of work to do, and construction is expected to take 4 years to complete.
We have spent the first 18 months completing a significant programme to underground utilities including power to increase capacity and bolster the security of the electricity supply to Queenstown Events Centre, Queenstown Airport, Jacks Point and beyond. We’ve moved and improve fibre and gas removed trees, and installed a 1.4 diameter, 700m long stormwater pipe and stormwater filter that not only takes state highway stormwater runoff, but also provides capacity for future land development to the north of SH6. Most of this work has been done overnight to reduce disruption to the state highways and the Frankton intersection.
We know 4 years is a long time and that road works are frustrating, but we are now 1/3 of the way through the project.
Several factors influence the timeframe:
We are undergrounding overhead power lines in the Gray/McBride intersection area. We are also moving services such as fibre and gas from under that intersection.
Gray and McBride intersection.
The new Frankton Golf Centre entry and driveway.
This is a partnership between NZ Transport Agency Waka Kotahi, Queenstown Lakes District Council and four design and construction companies, Beca, WSP, Downer New Zealand and Fulton Hogan. The partnership has been set up as an alliance model and has been gifted a name by Iwi: Kā Huanui a Tāhuna.