Waka Kotahi is widening the existing footpath on the northern side of SH2 Hewletts Road between Totara Street and Aerodrome Road to make it safer for people who are walking and cycling.
Works are underway and are expected to take around three months – scheduled for completion in June 2023 (weather dependent). To minimise the disruption to businesses and road users, works will be undertaken in four consecutive stages.
Work has started at ‘Work area 1’ and is subsequently moving up the road and work in one area at a time for two to three weeks, weather permitting.
The objective of the shared path is to improve safety, connectivity and accessibility for people who already walk and cycle in the area.
The number of cyclists using SH2 Hewletts Road is increasing and there are safety concerns and constraints with the existing footpath.
We are proposing to widen the existing footpath on the northern side of Hewletts Road from Totara Street to Aerodrome Road – a 1.4km stretch.
The current footpath is 1.4m wide and we are proposing to make it approximately 2m wide to allow multiple users such as pedestrians, scooters, mobility scooters and cyclists to share the path.
The proposal for the shared path involves widening the footpath within the road reserve, so no additional land is required.
We aim to deliver a solution which provides safety for pedestrians and cyclists while also maintaining essential access for businesses. We have developed a detailed design with feedback from cyclists, adjacent businesses and an independent Road Safety Audit.
This shared path is in addition to the shared path currently under construction along Totara Street, which is being led by Tauranga City Council and supported by Waka Kotahi, and will connect Totara Street and the harbour bridge shared path with Maunganui Road and the Mount area.
Key design features include:
Early 2023 – Construction starts
Mid-2023 – Construction expected to be complete