Commercial Vehicle Safety Programme – Auckland Port area

This work is part of a nationwide project called the Commercial Vehicle Safety Programme (CVSP), formally known as Weigh Right, which is developing an integrated network of cameras, weigh-in-motion scales and safety centres covering strategic routes across New Zealand.

The programme aims to ensure a level playing field for the industry, encourage compliant vehicle productivity, and improve road safety through targeted enforcement.

The Commercial Vehicle Safety Programme (CVSP) 

In Auckland, we will be installing weigh-in-motion technology at five sites in the Port area. This will include weigh scales and cameras (WIM) and overhead electronic signage (VMS).

  • SH1 eastbound by Grafton Bridge (WIM technology) - completed
  • SH16 eastbound by Symonds Street (WIM technology) - completed
  • SH16 eastbound on Stanley Street (VMS) - completed
  • SH16 westbound on The Strand (WIM technology) – Summer 2025
  • SH16 westbound on The Strand (VMS technology) – Summer 2025

Port locations

Upcoming closures 2024

This schedule will be updated as more dates are confirmed. Please note this work is weather dependent and dates advertised may change.

Update (2 October): We are excited to announce the projects at Grafton Bridge, Symonds Street and Stanley Street are almost complete.  The final stage will require a few night shifts to connect and test the equipment.

Site Dates and times Impact

SH16 The Strand

Proposed January 2025

To be advised closer to the time.

SH1 Bombay southbound

  • Sunday 3 to Thu 7 November

Between 9pm and 5am

Full closure southbound between Ramarama and Mill Road.

Ramp closures:

  • Ramarama southbound on-ramp and off-ramp.
  • Mill Road southbound off-ramp.

Recommended detour:

  • Via Great South Road and Mill Road.

SH1 Bombay northbound

  • Sun 10 to Thu 14 November
  • Sun 17 to Thu 21 November

Between 9pm and 5am

Full northbound closure between Nikau Road and Mill Road.

Ramp closures:

  • Nikau Road northbound on-ramp.
  • Beaver Road northbound off-ramp and on-ramp.
  • Mill Road northbound off-ramp.

Traffic management:

  • Traffic will still be able to travel north using one of the southbound lanes.

 

SH1 between Northcote Road and Constellation Drive paving works

There will be night closures on State Highway 1 (SH1) between Northcote Road and Constellation Drive between Monday 21 October and Thursday 5 December while our team can carry out paving rehabilitation on the state highway.  

This work is weather dependent and may change from advertised dates. For real time updates go to NZTA Journey Planner.

NZTA Journey Planner(external link)

Lanes

Dates

Impact

Southbound
From Constellation Drive to Northcote Road
(9pm and 5am)

  • Sun 3 & Mon 4 Nov (contingency)

Motorists: There will be a full southbound closure, and the following ramps will be closed:

  • Constellation Drive southbound on-ramp
  • Tristram Avenue southbound off-ramp and on-ramp
  • Northcote Road southbound off-ramp

Detour via Constellation Drive, East Coast Road, Forrest Hill Road, Wairau Road, Taharoto Road and Northcote Road.

Residents: There will be increased levels of noise as the team carry out reconstruction and resurfacing of the road.

Northbound
From Tristram Avenue to Constellation Drive
(9pm and 5am)

  • Wed 6 Nov
  • Thu 7 Nov
  • Sun 10 Nov
  • Thu 14 Nov
  • Sun 17 Nov
  • Mon 18 Nov
  • Tue 26 Nov
  • Wed 27 Nov
  • Thu 28 Nov
  • Sun 1 to Thu 5 Dec (contingency)

Motorists: There will be a full northbound closure, and the following ramps will be closed:

  • Tristram Avenue northbound on-ramp
  • Constellation Drive northbound off-ramp

Detour via Tristram Avenue, Forrest Hill Road, East Coast Road and Constellation Drive.

Residents: There will be increased levels of noise as the team carry out reconstruction and resurfacing of the road.