This summer NZ Transport Agency Waka Kotahi will be carrying out three essential maintenance projects on the Central Auckland motorway network. We appreciate that these works will be disruptive to motorists and the community. These dates have been chosen because traffic volumes are lower-than-normal during this period, which will help to reduce disruption. To avoid delays we highly recommend using alternative routes where possible.
From 9pm Thursday 26 December 2024 to 5am Monday 6 January 2025, NZTA will be replacing a bridge joint on the State Highway 1 (SH1) southbound lanes approximately 40 metres north of Grafton Road overpass on SH1. This work is weather dependent and advertised dates may change.
Day works (6am to 9pm):There will be lane restrictions on State Highway 1 southbound from Hobson Street on-ramp to Grafton Road on-ramp.
Night works (9pm to 6am):There will be a full southbound closure on State Highway 1 from Victoria Park Viaduct to Grafton Road on-ramp.
From 2am Thursday 26 December 2024 to 5am Monday 6 January 2025 NZTA will be carrying out several maintenance activities on the Auckland Harbour Bridge, including resurfacing of lanes, and maintenance underneath the bridge. There will be lane restrictions 24/7 but traffic will still be able to travel in both directions at all times.
We use a specialist surfacing system on the steel decks of the clip-ons, which takes two to three days to cure. During this time there may be no one working on the lanes, but we will still be working underneath the bridge.
During work on southbound clip-on lanes (1 & 2) Shelly Beach Road off-ramp will be closed and Shelly Beach Road will be closed from Westhaven. Signposted detours will be in place.
During work on northbound clip-on lanes (1 & 2) Curran Street on-ramp and Stafford Road off-ramp will be closed. Signposted detours will be in place.
There will also be ongoing maintenance work over the summer period from 24 November 2024 to 27 March 2025, excluding the above period when we are carrying out other work over Christmas and New Year. These works will be carried out at nighttime. Traffic will still be able to travel in both directions at all times.
From 19 January to April 2025 we will be carrying out three projects (The Strand rehabilitation, Strand Optimisation Project – stage 1 improvements and Commercial Vehicle Safety Programme) under a combination of weeknight shifts and Super Weekends. By combining these projects, we remove the need to return to the area later in the year and extend the disruption.
Because these projects involve paving and are weather dependent it is best carried out during the warmer months (January to April).
Things to note:
Works | Activity |
Preparation works SH16 Stanley Street and The Strand |
Curb and channel realignments in preparation for rehabilitation and The Strand Optimisation project activities. |
Road rehabilitation SH16 The Strand westbound lanes (Between 39 to 125 The Strand) |
Replacing concrete sheets that sit approximately 0.5m underneath the road surface on the westbound lanes. |
CVSP WIM – stage 1 SH16 The Strand, between Gladstone Road and St Georges Bay Road - westbound |
Excavation and resurfacing works to strengthen the road surface. Once resurfacing is complete it will take approximately 6 weeks for the surface to fully harden and the scales to be installed. |
The Strand Optimisation project – stage 1 |
|