This page relates to the 2018-21 National Land Transport Programme.
Application of Waka Kotahi NZ Transport Agency's Investment Assessment Framework is linked to the development of the activity through the Business Case Approach. Business cases are assessed to ensure they are fit for purpose and consistent with the principles of the business case approach, before they are assessed against the Investment Assessment Framework as shown below.
Business cases are developed progressively depending on the nature of the activity. Provided the business case passes assessment at the end of a phase, the activity is then assessed using the Investment Assessment Framework to build an Investment Profile and indicate the degree of investment commitment that Waka Kotahi makes to the activity.
Specific guidance for the assessment of the business case is provided at Assessment of the business case.
The criteria in the Waka Kotahi Investment Assessment Framework are used to assess improvement activities for support and investment approval. An activity's assessment profile is progressively developed through the business case process and is confirmed in full at the detailed business case stage. The point of entry and the number of cases that need to be developed will vary depending on the size, cost, complexity and risk of the proposed improvement.
How an activity's assessment profile is progressively developed through the business case process:
Business case stage |
Results Alignment assessment |
Cost-Benefit appraisal |
Degree of investment commitment at end of stage |
Indicative |
Not applicable |
Support case Consider funding for next stage |
|
Confirmed |
Indicative (conditional where appropriate) |
Support case Consider funding for next stage |
|
Indicative business case |
Reconfirmed (continued alignment) |
Indicative (conditional where appropriate) |
Consider funding for next stage |
Reconfirmed (continued alignment) |
Confirmed |
Consider funding for next stage |
|
Implementation |
Reconfirmed (continued alignment) |
Reconfirmed |
|
Support of strategic and programme business cases provides approved organisations and Waka Kotahi with:
Support of these stages does not commit Waka Kotahi to investing in the programmes or activities subsequently identified to address the issues. Approval of funding for a subsequent stage in the process is a separate step which will consider the business case assessment profile, its priority relative to other cases, any changes that have occurred as a result of new information, and the availability of funding in the relevant activity class.
Close
Waka Kotahi may not support a programme business case in its entirety. There may be elements that Waka Kotahi is prepared to support, and consequently assist their funding, and other elements that do not align with the GPS and which cannot be funded from the NLTF.
If support is limited to particular elements of a programme at the time of assessment these will be documented, with accompanying reasoning, in Transport Investment Online(external link).
Close
A strategic case must be established for all activities to be considered for investment. The strategic case will be reviewed at each investment gate. Waka Kotahi will assess strategic cases for their Results Alignment, once these cases have been agreed with stakeholders. This will indicate how well the issues identified, along with the benefits, align with the results/outcomes set out in the GPS.
If the strategic case is not aligned with the GPS results, subsequent business cases will not be funded through the NLTF.
A rating of Medium or High Results Alignment should enable Waka Kotahi to support the strategic case, and the activity should be able to progress further through the Business Case Approach with funding from the NLTF, subject to funding availability and programme optimisation.
Close
Programme business cases will be assessed by Waka Kotahi to confirm they provide indicative ratings for Results Alignment and Cost-benefit Appraisal. The benefit-cost ratio (BCR), should be a range, reflecting the spread of potential benefits, costs and risks of the preferred programme(s) to achieve the benefits identified in the strategic case.
Waka Kotahi will support the programme business case if:
In some situations Waka Kotahi will support the direction of a programme business case but may decide not to invest in subsequent business cases. This could happen where a proposed programme does not include sufficient transport benefits, and therefore is not eligible for NLTF funding, but it does provide targeted outcomes, e.g. in land use or economic development, that support the desired shape of the transport network.
Close
Although Waka Kotahi will endeavour to provide long term certainty to its investment partners, it will need to review its support from time to time. Some of the reasons for reviewing support are:
Waka Kotahi support does not mean an ongoing guarantee of funding, due to a number of factors, including:
Following its support of strategic cases, and programme business cases for significant investment proposals, Waka Kotahi will assess subsequent business cases when the activities are progressed to the next investment gates, to decide whether to invest in these. Its approval of funding for subsequent cases confirms Waka Kotahi support for the assessed case, i.e. there is no formal support for business cases after the strategic case/programme business case.
Full assessment profiles are required at each business case stage, which should be refined as the activity is progressed through the business case approach.
Close
Following development of the detailed business case, Waka Kotahi expects funding applications to cover the full implementation phase. The detailed business case should have been developed to a level that provides sufficient confidence to undertake all the steps involved in implementing the activity. Waka Kotahi discourages the splitting of implementation into a pre-implementation phase (covering design) and full implementation phase funding applications, other than for very large, complex and high risk activities.
CloseContinuous programmes are made up of a group of activities that relate to existing assets and services that are required to be delivered. The aim of the programme is to maintain an adequate level of service for its customer base. Examples are road maintenance programmes, existing public transport services, promotion of road safety and the road policing programme.
The way the Business Case Approach and Investment Assessment Framework are applied to continuous programmes differs from improvements. Rather than a progressive development of the business case through a largely linear process, their application to continuous programmes is cyclic with the investment gate being the periodic funding approvals linked to development of the next NLTP.
The principles of the Business Case Approach apply to continuous programmes through:
Close
The foundation for applying the Business Case Approach to continuous programmes is activity management planning, documented in:
The Activity Management Planning Cycle (currently being updated) section provides guidance on the continuous process of updating and improving activity management planning documents.
The activity management planning document should demonstrate that the proposed programme represents value for money by doing the:
In doing so it achieves desired outcomes and benefits from addressing the key issues and/or the contextual state of play in the area covered by the plan.
Underpinning this approach is robust evidence that supports the investment proposed in the plan.
Close
Waka Kotahi support for activity management programme business cases proposed by approved organisations or Waka Kotahi will be based on assessment of the plan demonstrating that the programme meets the expectations of the BCA approach and its fitness for purpose, value for money and alignment to GPS results.
CloseWaka Kotahi considers the statement of regional land transport priorities and, where required, the regional priority assigned to each activity, when assessing and prioritising activities for inclusion in the NLTP. Robust application of Business Case Approach principles to the Regional Land Transport Plan (RLTP) will help to inform this process.
The application of the Business Case Approach principles to Regional Land Transport Plans will assist in the:
The regional transport committee's assessment of its RLTP, required under the Land Transport Management Act, is made at a whole of RLTP level and, therefore, does not determine the individual assessment for each activity. The whole of RLTP assessment will, however, inform the assessment that Waka Kotahi makes for each activity. Each activity must be submitted to the RLTP with an assessment by the activity owner.
Close