This section provides a summary of the NZ Transport Agency's planning, funding and procurement delegations.
The Transport Agency has three levels of delegation:
This section summarises current planning, funding and procurement delegations. Transport Agency staff are advised to refer to the original Delegations page on the Transport Agency intranet, to ensure full understanding of the delegations.
The Transport Agency Board has agreed that Approved Organisations may receive delegated power to make funding approvals for small improvement projects up to $5 million construction/implementation cost per activity, provided that:
In effect, the Instrument of Delegation is from the Group Manager Planning & Investment to the Approved Organisation. The formal agreement is between the relevant Regional Manager Planning & Investment and the Approved Organisation, and sets out the respective responsibilities, including meeting Transport Agency expectations, principles and policy, as detailed in this Knowledge Base.
Organisations have delegated authority to manage programmes of activities, which may include the authority to transfer approved allocated funds between work categories and activity classes within the programme subject to terms and conditions formally advised by the Transport Agency (Planning & Investment). These programmes are:
The following diagram summarises the flow of delegated authority from the Transport Agency Board to staff and Approved Organisations.
The Transport Agency requires that all investment decisions are made by:
Those making investment decisions under delegation shall ensure that:
Failure to meet Transport Agency expectations in exercising delegations may result in the full or partial removal of authority to make decisions under delegation. The removal of delegations may be permanent or temporary and reinstatement of delegations may require evidence that any issue that led to their removal has been rectified.
Delegations may also be removed by the Group Manager Planning & Investment, where he considers that the risk to Transport Agency investment has grown to an unacceptable degree.
Scenario |
Delegate |
Set funding assistance rate for each Approved Organisation |
Board |
Approve variation to rate of funding assistance for specific projects |
Board |
Note: only if developed prior to the Business case Approach being implemented , i.e. developed during the 2012-15 NLTP.
Scale (Cost impact of strategy) |
Delegate |
Greater than $100 million |
Board |
Up to $100 million |
Group Manager P&I* |
Up to $60 million in Auckland/ Northland |
Regional Manager P&I - Auckland Northland |
Up to $30 million |
Regional Manager P&I - other regions |
* - "P&I" = Transport Agency Planning & Investment Group
- "HNO" = Transport Agency Highway & Network Operations Group, shown as Transport Agency (state highways) elsewhere in the Knowledge Base
Support Strategic Cases and approve funding for development of Programme Business Cases that are listed in the current NLTP* (under Work Category 004)
Scale (Cost impact of strategic case) |
Delegate |
Implementation cost is likely to be greater than $30 million ($60 million for Auckland/Northland) |
Group Manager P&I* |
Implementation cost is likely to be less than $60 million, for Auckland/Northland |
Regional Manager P&I - Auckland Northland |
Implementation cost is likely to be less than $30 million in regions other than Auckland/Northland |
Regional Manager P&I - other regions National Manager Network Directions & Performance (HNO) |
Varying the NLTP to add Programme Business Cases (under Work Category 004)
Significance |
Delegate |
All Programme Business Cases |
National Manager Investment |
Support Programme Business Cases (for approving funding once the Programme Business Case is complete see "Activities progressed under Business Case Approach" below).
Scale (Cost impact of strategy) |
Delegate |
Implementation cost is likely to be greater than $100 million. |
Board |
Implementation cost is likely to be less tha $100 million |
Group Manager P&I* |
Implementation cost is likely to be less than $60 million, for Auckland/Northland |
Regional Manager P&I - Auckland Northland |
Implementation cost is likely to be less than $30 million in regions other than Auckland/Northland |
Regional Manager P&I - other regions |
Approve funding and variations of RLTP development management, model development and activity management planning.
Funding Priority |
Delegate |
Included in the NLTP |
Regional Manager P&I National Manager Network Directions & Performance (HNO) |
Not included in the NLTP |
National Manager Investment |
Approving funding of any phase of an improvement activity developed prior to Business Case Approach.
Scale (construction cost including net property cost) |
Delegate |
Greater than $50 million |
Board |
Between $15 and $50 million |
Group Manager P&I |
Up to $15 million |
Regional Manager P&I National Manager Network Directions & Performance (HNO) |
Up to $5 million for Auckland Transport only |
Auckland Transport Chief Financial Office |
Approving funding for development and delivery of any business case beyond development of the Programme Business Case.
Scale (construction cost including net property cost) |
Delegate |
Greater than $50 million |
Board |
Between $15 and $50 million |
Group Manager P&I |
Up to $15 million |
Regional Manager P&I National Manager Network Directions & Performance (HNO) |
Up to $5 million for Auckland Transport only |
Auckland Transport Chief Financial Office |
Scale |
Delegate |
All |
Regional Manager P&I National Manager Network Directions & Performance (HNO) |
* Note that this does not include any funding approval.
Delegates should consider the scale and significance of the activity, and seek higher endorsement as appropriate.
Variations to the NLTP to add activities (other than Programme Business Cases).
For information on delegations for adding Programme Business Cases to the NLTP see the "Adding Programme Business Cases to the NLTP" section
Scale |
All activities within sub-delegate's funding approval* |
All activities outside of sub-delegate's funding approval |
All Values |
National Manager Investment - for nationally delivered activities Regional Manager P&I - for regionally delivered activities |
Group Manager P&I |
* Proposals to add Approved Organisation or state highway activities to the NLTP will require prior variation of relevant RLTPs, unless already included in an RLTP or exempt. See the Prior RLTP variation not required section of the Unlisted Activities and Programme Variations overview for exemptions.
Activity Class |
Scale |
Delegate |
Improvement activity, preventive maintenance activity, emergency works activity, or a minor improvements programme.
|
Greater than $5 million cumulative* |
Group Manager P&I |
Up to $5 million cumulative* |
Regional Manager P&I – Approved Organisation activities National Manager Network Directions & Performance (HNO) - state highway activities |
|
Approve and vary Maintenance and Public Transport programmes, nationally delivered Road Safety Promotion programmes and Sector Research activities |
All values within the limits of the activity class funding allocation by the Board |
National Manager Investment |
Provide recommendations for police activities |
All values |
Board |
Recommend variation to a Road Policing programme |
All values |
National Manager Investment |
* Cumulative means the total of all cost-scope adjustments, including the proposed adjustment, since funding for the activity was initially approved. If the cumulative cost-scope adjustment means that the project construction/implementation cost will exceed the delegated authority for approving funding of any phase or business case, the proposed cost-scope adjustment must be elevated for approval to the appropriate level of delegation.
* If the cost-scope adjustment results in a change in the funding priority of an activity, e.g. to less than "Reserve", this will trigger the Agency's significance policy and require the decision to approve the adjustment to be elevated.
* A decision on Significance needs to consider the impact of a scope change on the outcomes that will be delivered from the activity. If these are materially impacted, the significance of the proposed change should be viewed as High and would also require prior variation of the relevant RLTP.
Note that the limits are per event.
Scale (New approval and variations*) |
Delegate |
Greater than $15 million |
Group Manager P&I |
Up to $15 million |
Regional Manager P&I – Approved Organisation activities National Manager Network Directions & Performance (HNO) - state highway activities |
Up to $1 million (Emergency Works only) |
Planning and Investment Manager Senior Investment Advisor |
* If cumulative variations mean that the cost will exceed the delegated authority for approving funding of the activity, the proposed variation must be elevated for approval to the appropriate level of delegation.
Note that all variations are subject to NLTF cash-flow constraints.
Cost decreases (i.e. surplus funds are declared) Fiscally neutral cash-flow adjustments Fiscally neutral transfers within a Maintenance Programme |
Regional Manager P&I – for Approved Organisations* National Manager Network Directions & Performance (HNO) – for State Highways Manager National Programmes - for nationally delivered activities |
* Regional Managers may sub-delegate approval of fiscally neutral cost variations to Planning & Investment Managers and Senior Investment Advisors as appropriate.
Scale |
Materially impact delivery of GPS outputs |
Delivery of GPS outputs not impacted |
All |
Board |
Group Manager P&I |
* Where expenditure is likely to fall outside of the GPS range, the Minister's approval will be required to adjust the GPS range
Scale |
Delegate |
Use of the $150 million seasonal variation component |
Chief Financial Officer |
Use of the $100 million unexpected or unavoidable cost component |
Group Manager P&I |
All property purchased under work category 331.
Conditions |
Delegate |
Within the funding provisions set by the P&I Group, subject to any delegation set by the Board and provided it meets the conditions for work category 331 |
National Manager Network Directions & Performance (HNO) |
Decision |
Scale (annual procurement spend) |
Delegate |
Endorse procurement strategies |
Greater than $100 million |
Board |
Up to $100 million |
Group Manager P&I |
|
Up to $50 million and where the Regional Manager P&I considers the strategy to be minor to low risk |
Regional Manager P&I |
|
Endorse procurement strategy amendments |
Greater than $100 million unless the Chief Executive considers the amendments to be low risk |
Board |
Up to $100 million where the Group Manager P&I considers the amendments to be more than low risk |
Chief Executive |
|
Where the Group Manager P&I considers the amendments to be low risk |
Group Manager P&I |
|
Up to $30 million and where the Regional Manager P&I considers the amendments to be low risk |
Regional Manager P&I |
|
Approve procurement decisions under sections 25 & 26 of LTMA |
All values other than below |
Group Manager P&I |
Less than $30 million and where the Regional Manager P&I considers the decision to be low risk |
Regional Manager P&I |
Scale |
Delegate |
All values |
Regional Manager P&I |