Here we’ll keep you updated on timeframes, investment signals and key milestones to help you develop your funding proposals seeking inclusion in the 2024-27 NLTP.
This indicative timeline outlines the key dates, milestones and deadlines for the development of the 2024-27 NLTP.
This timeline remains indicative as there may be times when NLTP’s development is delayed, for example, due to late release of the Government Policy Statement on land transport (GPS), and we may adjust the timeframes for regional land transport plans (RLTPs) as a result.
Indicative dates for the 2024-27 NLTP development | |
---|---|
March 2024 |
Draft GPS issued. |
2 April 2024 |
Draft Investment Prioritisation Method (IPM) released for consultation. |
5 April 2024 |
NZTA and approved organisations modify their bids for continuous programmes in Transport Investment Online (TIO) following draft GPS and IPM. |
23 April 2024 |
NZTA and approved organisations submit final improvement activities. |
13 May 2024 |
Consultation closes on draft IPM. |
27 May 2024 |
NZTA releases indicative allocations for continuous programmes: maintenance, operations and renewals for local roads and state highways; public transport services and infrastructure (maintenance and operations); and road safety promotion. |
May-June 2024 |
Final GPS and final IPM published. |
1 August 2024 |
RLTPs approved by regional councils and submitted to NZTA. |
31 August 2024 |
NLTP is adopted. |
Early September 2024 |
NLTP and RLTPs are published. |
Frequently asked questions - indicative timeline for developing NLTP 2024-27 [PDF, 183 KB]
We recently completed a lessons learned exercise looking at how we can improve our processes and make things easier for the development of the next NLTP.
Report on lessons learned for the 2021-24 NLTP [PDF, 1.5 MB]