Full steam ahead on the largest road rebuild programme ever for Northland 

|

NZ Transport Agency Waka Kotahi (NZTA) has commenced one of the most significant road rebuild programmes in Te Tai Tokerau Northland over the next three years, as part of its annual summer renewal programme. 

This summer period, which runs from September through until May, you’ll notice NZTA busy around the Northland state highway network resealing, resurfacing and rebuilding sites across the region to ensure people can get to where they want, quickly and safely. 

Jacqui Hori-Hoult Regional Manager Maintenance and Operations NZTA says that this work is in addition to the regular maintenance of the network. 

“Along with our maintenance contractors, we’re planning to renew approximately 210.5 lane kilometres of state highway across Northland in the next eight months. 

“This significant additional investment will mean you can expect to see a lot more activity across the state highway network, especially during peak summer, where the warmer temperatures and dry air helps new seal stick to the road, ensuring a quality finish. 

“We appreciate that this increased activity will mean that your journey takes a little longer, so please plan ahead with the NZTA Journey Planner which accounts for all scheduled works on the state highway network.  

“This work is really important to improve our roads and provide a safer and more enjoyable drive for everyone” says Ms Hori-Hoult. 

Motorists are urged to watch out for road workers, adhere to temporary speed limits and follow the traffic management directions when driving through worksites.  

“We’re asking people to be patient with our crews as they set up and pack down worksites. Overtaking working vehicles can be dangerous for both workers and other drivers and everyone has the right to return to their whānau at the end of the day” says Ms Hori-Hoult. 

NZTA is working to minimise disruptions to road users while these important works are being completed. To keep traffic flowing as freely as possible, we’re making changes to the way we’re doing traffic management including programming work at night or during off-peak hours and pausing non-essential work on public holidays.  

To alleviate congestion over the Christmas and New Year holiday period, all work sites will close on Friday 20 December 2024, starting up again from Monday 6 January 2025. 

Key planned works are outlined below: 

Location  

Work activity  

Expected timeframe  

Expected impact  

SH14 Fudge Farm  

Road rebuild   

Mid-September to end November 2024 (eleven weeks)  

Expect dayworks and a 24/7 lane closure with stop/go  

SH14 Maunu Road   

Road resurfacing   

October 2024 (two nights) 

Expect nightworks and stop/go  

SH14 Maungatapere  (SH14/SH15 intersection) 

Road resurfacing   

October 2024 (one night)

Expect nightworks and stop/go  

SH1 Otaika Shops / Tarewa  

Road rebuild   

October 2024 (enabling works – three weeks) November 2024 (three weeks)  

Expect nightworks and stop/go  

SH11 Paihia  

Road resurfacing   

November 2024 (two weeks)   

Expect nightworks, stop/go and a detour 

SH1 Hikurangi  

Road rebuild   

November 2024 (four weeks)   

Expect nightworks, stop/go and a detour    

SH1 Kamo Bypass  

Road rebuild and resurfacing   

January 2025 (three weeks)   

Expect night closures, stop/go and detour via the Old State Highway (Kamo Road)  

SH1 Kawakawa Township  

Road rebuild  

February/March 2025 (three weeks)   

Expect nightworks and stop/go  

Note to editor: The figures used include between North Auckland (SH16 north of Woodhill and SH1 north of the Johnstone Hill Tunnels) to Te Reinga Wairua (Cape Reinga) which totals approximately 1892 lane kilometres.  