Emergency works on State Highway 2 between Bruce Road and Domain Road, Papamoa

|

Motorists travelling on State Highway 2 between Domain Road intersection and Bruce Road are advised lane diversions and temporary speed restrictions will be in place from this afternoon whilst emergency repairs continue to be carried out on the road surface.

As part of the NZ Transport Agency's (NZTA) Tauranga Eastern Link project, pre-load material (sand) is being laid adjacent to the highway to compact the ground beneath, to provide a firm base on which the new road will be constructed.

NZTA's Bay of Plenty State Highway Manager, Brett Gliddon, says that the weight of the pre-load and the associated settlement is causing cracks along this section of the highway.

"It is anticipated that some cracking to sections of this road surface may continue to occur until the pre-load is removed in approximately 12 months' time."

The northbound and southbound lanes will be moved across to one side and a 50km/h speed restriction will be in place. Night works will be carried out from 7.00pm tonight and at various times during these works a manual stop/go will be in place for southbound traffic only, and some delays may be experienced. Daytime works will continue over the weekend with completion expected to be on Monday 16 July, weather dependent.

Motorists are advised to plan their journey ahead of time, and to take extra care, as delays are to be expected while driving through this area.

The NZTA thanks motorists for their continued patience and assistance while this work is being undertaken.

Keep up-to-date with developments at www.nzta.govt.nz/tel.

Editor's notes

The four-lane Tauranga Eastern Link will run from Te Maunga (near Baypark Stadium) in Tauranga to the existing junction of State Highways 2 and 33 (the Rotorua and Whakatane highways) near Paengaroa. It will be made up of 17km of new road and an upgrade of six kilometres of existing highway. The new highway is expected to open to traffic in 2016.

The Government has identified seven essential state highway projects linked to New Zealand's economic prosperity. Called the roads of national significance, or RoNS for short, the NZTA is charged with delivering this programme of state highway improvements within the next 10 years. The RoNS programme represents one of New Zealand's biggest ever infrastructure investments and is a key part of the Government's National Infrastructure Plan and Government's Policy Statement for transport.

The seven RoNS projects are based around New Zealand's five largest population centres. The focus is on moving people and freight between and within these centres more safely and efficiently. Other RoNS may be added in future but currently from north to south the seven projects are:

More information is available at www.nzta.govt.nz/rons.

 

Tags