NTRO’s Intelligent Pavement Assessment Vehicle (iPAVE) will be surveying New Zealand’s State Highway Network annually, collecting vital data and providing information to determine future road maintenance and prioritise repairs and upgrades.
Data will be collected at traffic speed in a single pass, measuring both functional and structural conditions of the pavement at the same time. This will assist transport asset managers to make more informed decisions of where to spend maintenance dollars.
The iPAVE features deflection measurement technology, dual high-definition LiDAR, ground penetrating radar, real-time data processing and validation, more self-cleaning cameras, and pavement strength in both left and right wheel paths.
Find out more information about the iPAVE(external link)
Watch a video on the iPAVE4 (on LinkedIn website)(external link)
Check the table below for the survey start and end dates for the 2024/25 iPAVE survey programme in each area. This will be kept up to date so please check for the latest programme.
Last updated: 9 April 2025
Area | Projected duration | Projected start date | Projected end date |
---|---|---|---|
(NOC) Wellington | 4 Days | 3-Apr-25 | 7-Apr-25 |
Transmission Gully PPP | 1 Day | 8-Apr-25 | 8-Apr-25 |
Picton to Southland | 2 Days | 10-Apr-25 | 11-Apr-25 |
(NOC) Southland | 6 Days | 12-Apr-25 | 18-Apr-25 |
(NOC) Coastal Otago | 6 Days | 19-Apr-25 | 26-Apr-25 |
(NOC) Otago Central | 5 Days | 28-Apr-25 | 2-May-25 |
Milford | 1 Day | 3-May-25 | 3-May-25 |
(NOC) South Canterbury | 5 Days | 5-May-25 | 9-May-25 |
Validation + Calibration 2 | 5 Days | 10-May-25 | 15-May-25 |
(NOC) North Canterbury | 7 Days | 16-May-25 | 24-May-25 |
(NOC) West Coast | 8 Days | 26-May-25 | 3-Jun-25 |
(NOC) Nelson-Tasman | 4 Days | 4-Jun-25 | 7-Jun-25 |
(EC) Marlborough | 2 Days | 9-Jun-25 | 10-Jun-25 |
Validation + Calibration 3 | 5 Days | 12-Jun-25 | 17-Jun-25 |
(NOC) Taranaki | 6 Days | 18-Jun-25 | 24-Jun-25 |
(NOC) Manawatū-Whanganui | 7 Days | 25-Jun-25 | 2-Jul-25 |
(NOC) Hawkes Bay | 5 Days | 3-Jul-25 | 8-Jul-25 |
(NOC) Tairawhiti | 3 Days | 9-Jul-25 | 11-Jul-25 |
(NOC) Bay of Plenty East | 5 Days | 12-Jul-25 | 17-Jul-25 |
(NOC) Bay of Plenty West | 2 Days | 18-Jul-25 | 19-Jul-25 |
Validation + Calibration 4 | 5 Days | 21-Jul-25 | 25-Jul-25 |
(NOC) East Waikato | 5 Days | 26-Jul-25 | 31-Jul-25 |
(NOC) Central Waikato | 7 Days | 1-Aug-25 | 8-Aug-25 |
(NOC) West Waikato | 6 Days | 9-Aug-25 | 15-Aug-25 |
Auckland Alliance | 6 Days | 16-Aug-25 | 22-Aug-25 |
Pūhoi to Warkworth Motorway | 1 Day | 23-Aug-25 | 23-Aug-25 |
(NOC) Northland | 9 Days | 25-Aug-25 | 3-Sep-25 |