Greater Wellington Regional Council
To seek the Board's approval for funding the design and construction of Greater Wellington Regional Council's urban rail stabling and depot for new electric multiple units in the Wellington Region
26 November 2008
The NZ Transport Agency Board:
The stabling and depot project is a small but essential part of the Wellington urban rail system upgrade. It is an effective project that needs to be implemented as soon as possible to ensure the earliest commissioning of the soon to be arriving Matangi EMU's which is essential to ensure the delivery of the outputs of the Wellington Commuter Rail Business Case 2004. As part of the Wellington Rail Business Case 2004 it has a funding profile of HHL.
This Wellington stabling and depot project is on the critical path of urban rail projects in Wellington now that the new EMUs have been ordered. In the knowledge that the Chief Executive of KiwiRail has endorsed the concept and will be party to the sign off on the final design, we recommend that the Board approve funding for the Wellington Depot and Stabling Project from N funds.
We confirm that the matters in sections 20(2) and 20(5) of the LTMA have been satisfied and that the matters in section 20(3) have been taken into account.
If you would like details of how the assessment profile for this activity was determined, please email us at boardsecretariat@nzta.govt.nz.