Lower North Island/Upper South Island - Planned state highway roadworks

|

Important information for drivers.

North Island:

  • There will be maintenance closures for The Terrace Tunnel (Monday night) and Mt Victoria Tunnel (Tuesday night) on SH1 in Wellington. The closures will run from 9 pm to 4:30 am. Drivers travelling through the city will have to use alternate routes and can expect longer travel times.
  • Work begins this weekend in Featherston on a safer new pedestrian crossing on State Highway 2.

South Island:

The details below outline the main planned state highway roadworks occurring in the greater Wellington region and the top of the South Island over the coming week (from Saturday, 11 November). Further details about regional state highway conditions and roadworks are also published on our website:

NOTE: Roadworks are dependent on weather and other factors. Bad weather can see work postponed to the next suitable night in the works programme.

Wellington, Porirua, Kāpiti, Hutt

State Highway 1

SH1 Tunnel CLOSURES  

  • Terrace Tunnel, Monday night, 9 pm-4.30 am
  • Mt Victoria Tunnel, Tuesday night, 9 pm-4.30 am  
  • CLOSED for maintenance 

SH1 Newlands, RAMP CLOSURES 

  • Northbound onramp, Sunday night, 7 pm-4.30 am 
  • Onramp CLOSED for asphalt resurfacing
  • Southbound offramp, Friday morning, 2 am-4.30 am 
  • Offramp CLOSED for underground service work 

SH1 Porirua, SOUTHBOUND ROAD CLOSED from Kenepuru Link Road to Tawa interchange (external link)

  • Monday and Tuesday nights, 7 pm-4.30 am 
  • SOUTHBOUND ROAD CLOSED for gantry installation and asphalt resurfacing
  • Signposted detour via local roads to Tawa interchange

SH1 Mackays Crossing, LOCAL ROAD CLOSED UNDER CROSSING  

  • Friday night, 5 pm-5 am 
  • LOCAL ROAD CLOSED for asphalt resurfacing
  • Signposted detour for local traffic 

Old SH1, Ōtaki River Bridge(external link)

  • Monday to Friday, 9 am-3 pm (until early December)
  • Stop/go traffic controls for bridge assessment

SH1 North of Ōtaki to Manakau

  • Monday to Thursday nights, 7 pm-5 am
  • Various sites
  • Stop/go traffic controls for chipseal resurfacing 

Old SH1, Peka Peka  

  • Friday during the day, 7 am-7 pm
  • Stop/go traffic controls for safety improvements project

State Highway 59 

SH59 Porirua, SOUTHBOUND ROAD CLOSED from Mungavin Ave to SH1 Tawa interchange (external link)

  • Monday and Tuesday nights, 7 pm-4.30 am 
  • SOUTHBOUND ROAD CLOSED for gantry installation and asphalt resurfacing
  • Signposted detour via local roads to Tawa interchange

SH59 Pukerua Bay, south of Gray Street 

  • Sunday night, 7 pm – 5.30 am
  • Stop/go traffic controls for sign renewals

State Highway 58     

SH58 Pauatahanui to SH1/SH58 interchange, EASTBOUND ROAD AND NORTHBOUND ONRAMP CLOSED  (external link)

  • Saturday 11, 5 am-5 pm 
  • ROAD CLOSED for asphalt resurfacing

SH58 Haywards Hill Road(external link)

  • Monday to Friday during the day, 9.30 am-3 pm
  • Stop/go traffic control for safety project

SH58 Paremata Road, near Joseph Banks Road 

  • Sunday night, 8 pm-6 am
  • Stop/go traffic controls for fibre installation 

SH58 Haywards Hill Road, near Mt Cecil Road  

  • Sunday night, 7 pm-5.30 am 
  • Stop/go traffic control for asphalt resurfacing

State Highway 2

SH2 Upper Hutt, Silverstream intersection to Gibbons Street intersection LANE CLOSED  

  • Wednesday and Thursday nights, 9 pm-4.30 am 
  • Northbound lane and Whakatiki St intersection CLOSED for asphalt resurfacing 
  • Signposted detour via Silverstream intersection, Fergusson Drive and Gibbons Street intersection  

SH2 Remutaka Hill, Featherston side

  • Saturday to Friday, day/night
  • Stop/go traffic control for slip repairs

SH2 South of Kaitoke, near Kaitoke Loop Road 

  • Wednesday during the day, 8 am-4:30 pm 
  • Stop/go traffic controls for chipsealing 

SH2 Kaitoke, near Kaitoke Bridge 

  • Tuesday during the day, 8 am-4.30 pm 
  • Stop/go traffic controls for chipsealing 

Wairarapa State Highways

State Highway 2      

SH2 Waingawa, Norfolk and Wiltons roundabouts CLOSED SOUTHBOUND 

  • Sunday and Monday nights, 7 pm-6 am
  • Road CLOSED for chip sealing
  • Signposted detour via local roads

SH2 Masterton to Carterton, safety improvement works(external link)

  • Wednesday, 1 November to Thursday, 14 December, Sunday to Thursday nights, 8 pm to 6 am.
  • Road surfacing works
  • Contractors will begin to set up traffic management from 7 pm.
  • While the work is underway, southbound traffic may have to detour via Cornwall Rd and Hughes Line.

SH2 Remutaka Hill, Featherston side

  • Saturday to Friday, day/night
  • Stop/go traffic control for slip repairs

SH2 South of Featherston, near Moore Street 

  • Wednesday night, 7 pm-5.30 am
  • Stop/go traffic controls for sign replacement

SH2 Featherston, near Lyon Street/Birdwood Street (external link)

  • Sunday to Thursday nights, 7 pm-5.30 am
  • Stop/go traffic controls for raised pedestrian crossing project

SH2 North of Carterton, near Park Road 

  • Sunday to Tuesday nights, 7 pm-6 am
  • Stop/go traffic controls for wastewater works

SH2 Waingawa, near Ngaumutawa Road 

  • Tuesday to Thursday nights, 7 pm-6 am
  • Stop/go traffic controls for asphalt resurfacing

SH2 Ōpaki, at Loopline and Wingate Road 

  • Monday during the day, 8 am-4.30 pm
  • Stop/go traffic controls for chipseal resurfacing

SH2 Several locations between Kiriwhakapapa and Mount Bruce (external link)

  • Monday to Friday during the day, 8 am-4.30 pm
  • Stop/go traffic controls for barrier installation

SH2 North of Mount Bruce(external link)

  • Monday to Friday during the day, 8 am-4.30 pm
  • Stop/go traffic controls for road reconstruction

State Highway 53                                                      

SH53 Featherston, SH2 and SH53 junction 

  • Thursday, 8 am – 4.30 pm
  • ROAD CLOSURE for chipsealing
  • Signposted detour via local roads

SH53 Featherston, near Phillips Line 

  • Thursday during the day, 8 am – 4.30 pm
  • Stop/go traffic controls for chipsealing

Marlborough State Highways

State Highway 1                                                          

Travellers going through Picton need to be aware of ongoing work on Dublin Street. A closure is in place until approximately March 2025, while a new overbridge and other infrastructure is built. More details can be found on the Marlborough District Council website and on the iRex project website

State Highway 6

  • No major works planned

State Highway 63

SH63 - Renwick

  • Monday and Tuesday, 7 am – 4 pm
  • Pre-seal works
  • Stop/Go Traffic Management

SH63 - Waihopai

  • Tuesday and Wednesday, 7 am – 4 pm
  • Pre-seal works
  • Stop/Go Traffic Management

State Highway 62

  • No major works planned

Nelson/Tasman State Highways

State Highway 6

SH6 Rai Saddle(external link)

  • Tuesday, 31 October to mid-December, Monday to Friday, 7 am - 6 pm
  • Stop/go with a temporary speed limit of 30km/h
  • Slip and rock fall repairs
  • Drivers can expect short delays of up to 15 minutes
  • No weekend works planned

SH6 Foxhill, Wakefield to Belgrove(external link)

  • Monday, 9 October to Friday, 15 December. 7 am – 6 pm (Mon-Fri)
  • Possibility of Saturday works at times as may be required
  • Temporary Speed Limit of 30km/h. Road users can expect travel delays of around 15 minutes.
  • Road reconstruction work
  • During nights and weekends when no work is taking place, a 50km/h speed restriction will be in place

SH6 Whangamoa Hill, east of Wakapuaka Bridge

  • Daily, 24/7
  • Single lane closure with stop/go and 30 km/h traffic management,
  • A shoulder closure will be in place at night.
  • Slip repair works
  • Expect short travel delays.

SH6 Dellow’s Bluff, Murchison

  • 30 km/h speed restrictions.  Road is open to two lanes
  • Rockfall area

State Highway 65

  • No major works planned

State Highway 63

  • No major works planned

State Highway 60

SH60 Tākaka Hill Night closures(external link)

  • 29 October to 24 November, Sunday to Thursday 8 pm - 5:30 am
  • Resurfacing, road repairs and general maintenance
  • The road will be opened once each night of the closures.
  • There will also be Stop/Go traffic management from Tuesday 14th November to Friday 17th November, between 6 am and 6 pm for resurfacing works.

SH60 Motueka, Lyndhurst Drive to Parker St

  • Stop/Go traffic management, local road detours and temporary speed restrictions
  • Wastewater works – Tasman District Council project
  • Short traffic delays expected
  • Ongoing until May 2024(external link)

SH60 Bird’s Hill, Golden Bay

  • Road is open to two lanes, 50km speed restriction.
  • Road underslip work.

 

 