NZ Transport Agency Waka Kotahi (NZTA) is advising drivers to expect ongoing delays this week getting to and from Port Chalmers as contractors continue to make SH88 safe for two-way traffic. To make the most of the workday, hours have been extended to start at 7 am and finish at 6 pm.
Investigations to date after last week’s downpour have shown much more material needing to be removed than initially assessed and some huge boulders have to be broken up first, says NZTA Journey Manager Nicole Felts.
“We appreciate these delays at more than one site could add up to 30 minutes to the trip between Port Chalmers and Forsyth Barr Stadium,” says Miss Felts. “Thanks to all road users for building in the time.”