Check out the progress made on the repairs to State Highway 1 through Mangamuka Gorge.
This flyover of the entire site, carried out at the beginning of July 2024, shows how much has changed onsite compared to the previous flyover from December 2023. We're on track to reopen the road by Christmas 2024. We're currently working on all the critical slips – we've finished piling on nine of the slips, three of which are complete, and we've just drilled the final 1050 millimetre diameter piles for slips A1 / A2. We'll get underway with physical works on the newest slip, A47, in early August 2024.