Phase |
Regional priority |
Profile |
Status |
Work category |
Indicative FAR* |
Total phase cost |
2009/10 NLTF ($000) |
2010/11 NLTF ($000) |
2011/12 NLTF ($000) |
Funding priority |
Funding source* |
Nelson City Council |
Renewal of local roads |
Road renewals |
Local Roads |
|
|
App. |
|
|
5,042.8 |
712.2 |
715.3 |
740.9 |
|
N |
Operation and maintenance of local roads |
Road operations and maintenance |
Local Roads |
|
|
App. |
|
|
7,234.6 |
1,008.8 |
1,046.6 |
1,055.4 |
|
N |
New & improved infrastructure for local roads |
Minor improvements 2009/12 |
Local Roads |
|
|
App. |
341 |
|
- |
137.7 |
125.4 |
126.0 |
|
N |
Improve, expand or replace network group |
Group allocation |
|
|
Alloc. |
|
|
|
50.0 |
55.0 |
55.0 |
|
|
Retaining Wall renewals 2009/12 |
Construction |
- |
MMM |
Cat2 |
322 |
53% |
427.6 |
31.8 |
155.5 |
39.3 |
Probable |
R |
Public transport infrastructure |
General access & community benefits PT group |
Group allocation |
|
|
Alloc. |
|
|
|
197.8 |
197.8 |
197.8 |
|
|
Bus Stop upgrades 2008/09-2010/11 |
Construction |
- |
LMM |
Reserve |
531 |
60% |
696.2 |
- |
- |
254.4 |
Res. A |
|
Nelson and Stoke bus interchange infrastructure 2009/10 |
Construction |
- |
LMM |
Reserve |
531 |
60% |
264.5 |
- |
9.3 |
149.4 |
Res. A |
|
Waimea/Ridgeway Intersection 2009/10-2010/11 |
Investigation |
- |
LMM |
Reserve |
533 |
53% |
20.0 |
10.6 |
- |
- |
Res. A |
|
Waimea/Ridgeway Intersection 2009/10-2010/11 |
Construction |
- |
LMM |
Reserve |
533 |
53% |
318.0 |
- |
- |
168.5 |
Res. A |
|
CBD bus priority intersections & Rutherford St 2-laning09/10 |
Construction |
- |
LMM |
Reserve |
533 |
53% |
79.5 |
- |
- |
42.1 |
Res. A |
|
Beatson Rd and roundabout PT improvements 2010-2012 |
Construction |
- |
LMM |
Reserve |
533 |
53% |
127.0 |
- |
2.7 |
64.6 |
Res. A |
|
Waimea Rd bus priority lanes 2009/10 |
Construction |
- |
LMM |
Reserve |
533 |
53% |
317.5 |
- |
8.2 |
160.1 |
Res. A |
|
Urban transport choice, network improvements & safety PT group |
Group allocation |
|
|
Alloc. |
|
|
|
110.9 |
110.9 |
110.9 |
|
|
Waimea / Motueka St Intersection 2008/09- 2010/11 |
Construction |
- |
LMM |
Reserve |
533 |
53% |
837.1 |
34.5 |
409.2 |
- |
Res. A |
|
Public transport services |
Bus & ferry concession fares |
Operations |
|
|
App. |
513 |
50% |
421.5 |
70.2 |
70.2 |
70.2 |
|
N |
Bus services |
Operations |
|
|
App. |
511 |
50% |
370.8 |
61.8 |
61.8 |
61.8 |
|
N |
Public transport facilities maintenance and operations |
Operations |
|
|
App. |
514 |
60% |
291.1 |
57.6 |
58.2 |
58.8 |
|
N |
Public transport professional services/ administration |
Operations |
|
|
App. |
|
50% |
150.0 |
25.0 |
25.0 |
25.0 |
|
N |
Total mobility flat payments |
Operations |
|
|
App. |
521 |
100% |
151.1 |
48.9 |
48.9 |
53.3 |
|
N |
Total mobility operations |
Operations |
|
|
App. |
517 |
50% |
634.5 |
105.7 |
105.7 |
105.7 |
|
N |
Wheelchair hoists |
Operations |
|
|
App. |
519 |
60% |
4.0 |
2.4 |
- |
- |
|
N |
Demand management & community programmes |
Community Focused Activites 2009/2012 |
Implementation |
|
|
App. |
432 |
75% |
- |
158.7 |
- |
- |
|
N |
Walking and cycling facilities |
Footpath Construction |
Construction |
3 |
|
Com |
451 |
53% |
1,336.0 |
80.0 |
230.0 |
- |
|
N |
Walking and Cycling - Key safety and congestion |
Group allocation |
|
|
Alloc. |
|
|
|
328.2 |
328.2 |
328.2 |
|
|
Transport planning |
Regional land transport planning management |
Implementation |
|
|
App. |
001 |
100% |
46.1 |
15.8 |
15.1 |
15.1 |
|
|
Activity Management Plans |
Study |
- |
MM_ |
Cat2 |
003 |
53% |
220.8 |
- |
51.8 |
28.1 |
|
N |
Studies & Strategies 2009-2012 |
Study |
- |
MM_ |
Cat2 |
002 |
75% |
447.7 |
266.3 |
69.5 |
- |
|
N |
Bridge Inspection Survey 2009/10 |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
Supergold card |
Supergold trip adminstration |
Implementation |
|
|
App. |
|
|
15.0 |
5.0 |
5.0 |
5.0 |
|
|
Supergold trip payments |
Implementation |
|
|
App. |
|
|
150.0 |
50.0 |
50.0 |
50.0 |
|
|
Nelson Highway & Network Operations |
Renewal of state highways |
Road renewals |
State Highways |
|
|
App. |
|
|
4,733.0 |
2,805.6 |
963.7 |
963.7 |
|
N |
Scour Investigation 9/12 |
Construction |
20 |
|
Cat2 |
241 |
100% |
46.0 |
15.0 |
15.0 |
16.0 |
|
|
Operation and maintenance of state highways |
Road operations and maintenance |
State Highways |
|
|
App. |
|
|
6,325.6 |
2,107.6 |
2,109.0 |
2,109.0 |
|
N |
New & improved infrastructure for State highways |
Cable Bay Road Intersection |
Investigation |
|
|
Com |
|
100% |
110.0 |
71.4 |
- |
- |
|
N |
SH6 Quarantine Road I/S |
Investigation |
|
|
Com |
|
100% |
150.0 |
135.0 |
- |
- |
|
N |
Minor improvements 2009/12 |
State Highways |
|
|
App. |
341 |
|
- |
317.3 |
210.7 |
210.7 |
|
N |
Improve, expand or replace network group |
Group allocation |
|
|
Alloc. |
|
|
|
1,875.0 |
2,062.5 |
2,062.5 |
|
|
Cable Bay Road Intersection |
Design |
2 |
MMH |
Cat2 |
324 |
100% |
52.0 |
52.0 |
- |
- |
Probable |
R |
Cable Bay Road Intersection |
Construction |
2 |
MMH |
Cat2 |
324 |
100% |
548.0 |
- |
548.0 |
- |
Probable |
R |
Rai Saddle second curve realignment |
Design |
7 |
MMH |
Cat2 |
324 |
100% |
206.0 |
206.0 |
- |
- |
Probable |
R |
Rai Saddle second curve realignment |
Construction |
7 |
MMH |
Cat2 |
324 |
100% |
2,610.0 |
- |
- |
1,308.0 |
Probable |
R |
SH6 Atawhai Drive Intersections |
Design |
5 |
MMH |
Cat2 |
324 |
100% |
163.0 |
77.0 |
86.0 |
- |
Probable |
R |
Improved Driver Information 9/12 |
Construction |
21 |
MMM |
Cat2 |
321 |
100% |
82.8 |
26.8 |
27.6 |
28.4 |
Probable |
R |
Nelson Region PL |
Investigation |
24 |
MMM |
Cat2 |
324 |
100% |
131.0 |
- |
- |
131.0 |
Probable |
R |
Pavement Smoothing 9/12 |
Construction |
17 |
MMM |
Cat2 |
324 |
100% |
483.8 |
163.0 |
166.9 |
154.0 |
Probable |
R |
Property Acquisitions 9/12 |
Property |
19 |
MMM |
Cat2 |
331 |
100% |
541.9 |
175.3 |
180.6 |
186.0 |
Probable |
R |
Rehabilitation Seal Widening 9/12 |
Construction |
23 |
MMM |
Cat2 |
324 |
100% |
103.5 |
33.5 |
34.5 |
35.5 |
Probable |
R |
Safety Retrofit 9/12 |
Construction |
9 |
MMM |
Cat2 |
324 |
100% |
310.6 |
100.5 |
103.5 |
106.6 |
Probable |
R |
SH6 Atawhai Drive Speed Management |
Investigation |
3 |
MMM |
Cat2 |
321 |
100% |
51.5 |
51.5 |
- |
- |
Probable |
R |
SH6 Atawhai Drive Speed Management |
Construction |
3 |
MMM |
Cat2 |
321 |
100% |
1,060.9 |
- |
1,060.9 |
- |
Probable |
R |
SH6 Gentle Annie Passing Lanes |
Design |
6 |
MMM |
Cat2 |
324 |
100% |
57.0 |
57.0 |
- |
- |
Probable |
R |
SH6 Gentle Annie Passing Lanes |
Construction |
6 |
MMM |
Cat2 |
324 |
100% |
2,191.0 |
- |
2,191.0 |
- |
Probable |
R |
SH6 The Glen Intersection Improvements |
Investigation |
4 |
MMM |
Cat2 |
324 |
100% |
83.0 |
- |
83.0 |
- |
Probable |
R |
Strategic Plan Initiatives 9/12 |
Construction |
18 |
MMM |
Cat2 |
324 |
100% |
248.5 |
80.4 |
82.8 |
85.3 |
Probable |
R |
Teal River Bridge |
Design |
8 |
MMM |
Cat2 |
324 |
100% |
154.5 |
154.5 |
- |
- |
Probable |
R |
SH6 Whangamoa South Realignment |
Design |
10 |
|
Reserve |
|
|
1,331.5 |
|
|
|
Res. B |
|
SH6 Whangamoa South Realignment |
Property |
10 |
|
Reserve |
|
|
347.9 |
|
|
|
Res. B |
|
Demand management & community programmes |
Community Advertising 9/12 - Nelson |
Implementation |
|
|
App. |
432 |
100% |
- |
19.1 |
- |
- |
|
N |
Walking and cycling facilities |
Atawhai W/C project |
Construction |
- |
|
Com |
452 |
100% |
1,275.0 |
31.6 |
- |
- |
|
N |
Transport planning |
Activity management plans |
Study |
|
|
Cat2 |
003 |
100% |
182.2 |
78.2 |
52.0 |
52.0 |
|
N |
Nelson Safe, Sustainable and Efficient Routes |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|