National Land Transport Programme 2009-2012

Marlborough regional NLTP table

Return to Marlborough regional tables page

Phase Regional priority Profile Status Work category Indicative FAR* Total phase cost 2009/10 NLTF ($000) 2010/11 NLTF ($000) 2011/12 NLTF ($000) Funding priority Funding source*
Marlborough District Council
Renewal of local roads
Road renewals Local Roads App. 13,887.6 2,005.8 2,109.8 2,272.7 N
Operation and maintenance of local roads
Road operations and maintenance Local Roads App. 13,791.4 1,870.1 2,110.8 2,387.5 N
New & improved infrastructure for local roads
Bridge Replacement Programme 08/09 Construction - Com 322 56% 243.0 123.2 - - N
Minor improvements 2009/12 Local Roads App. 341 - 310.1 300.4 326.8 N
Improve, expand or replace network group Group allocation Alloc. 350.0 300.0 300.0
Jacksons Rd /Old Renwick Rd Intersection Upgrade 09/10 Construction 9 MMM Cat2 324 56% 637.0 356.7 - - Possible R/N
Unsealed Road Improvements Construction - MMM Cat2 324 56% 200.0 - 56.0 56.0 Possible R/N
User benefits improvements group Group allocation Alloc. - - -
Seal Extensions Construction 28 LMM Reserve 325 56% 1,096.0 109.8 168.0 336.0 Res. A
Public transport services
Bus services Operations App. 511 50% 374.9 58.3 64.1 65.0 N
Public transport facilities maintenance and operations Operations App. 514 60% 12.0 2.4 2.4 2.4 N
Public transport professional services/ administration Operations App. 50% 24.0 4.0 4.0 4.0 N
Total mobility flat payments Operations App. 521 100% 54.0 18.0 18.0 18.0 N
Total mobility operations Operations App. 517 50% 300.0 50.0 50.0 50.0 N
Wheelchair hoists Operations App. 519 60% 15.0 - 4.5 4.5 N
Demand management & community programmes
Marlborough Community Programme 2009/2012 Implementation App. 432 75% - 124.1 - - N
Transport planning
Regional land transport planning management Implementation App. 001 100% 80.6 27.7 26.5 26.4
Asset Management Planning Study - ML_ Cat2 003 56% 193.0 35.3 11.2 61.6 N
Rail freight and sea freight
Port Underwood Log Barging Construction - Com 442 57% 947.0 52.8 - -
Supergold card
Supergold trip adminstration Implementation App. 12.0 4.0 4.0 4.0
Supergold trip payments Implementation App. 45.0 15.0 15.0 15.0
Marlborough District Council SPR
Renewal of local roads
Road renewals SPR App. 67.0 65.0 1.0 1.0 N
Operation and maintenance of local roads
Road operations and maintenance SPR App. 94.0 30.0 31.0 33.0 N
New & improved infrastructure for local roads
Minor improvements 2009/12 SPR App. 341 - 7.6 2.3 2.4 N
Marlborough Highway & Network Operations
Renewal of state highways
Road renewals State Highways App. 7,565.1 2,590.3 2,487.4 2,487.4 N
Scour Investigation 9/12 Construction 20 Cat2 241 100% 164.0 53.0 55.0 56.0
Operation and maintenance of state highways
Road operations and maintenance State Highways App. 9,763.2 3,253.0 3,255.1 3,255.1 N
New & improved infrastructure for State highways
Awatere Bridge Construction 1 Com 322 100% 13,782.5 20.0 - - N
Lions Back Safety Improvements Design 3 Com 324 100% 288.4 288.4 - - N
Grovetown NB PL Construction Com 100% 789.9 30.0 - - R
Sneiders Creek Realignment Design Com 100% 205.0 200.0 - - N
Sneiders Creek Realignment Investigation Com 100% 124.9 9.3 - - N
Minor improvements 2009/12 State Highways App. 341 - 377.4 393.8 393.8 N
Lions Back Safety Improvements Property MMM App. 324 100% 637.7 315.0 322.7 - Probable R/N
Lions Back Safety Improvements Construction 3 MMH Cat2 324 100% 6,887.3 - 1,793.8 3,138.4 Probable R
Dashwood Overbridge Construction MMM Cat2 322 100% 6,753.9 - - 2,201.1 Probable R/N
Dashwood Overbridge Design 4 MMM Cat2 322 100% 206.0 206.0 - - Probable R/N
Dashwood Overbridge Property MMM Cat2 322 100% 104.5 51.6 53.0 - Probable R/N
Improve, expand or replace network group Group allocation Alloc. 2,156.3 2,371.9 2,371.9
SH1S Pukapuka Stream - Realignment Investigation 5 MMH Cat2 324 100% 103.0 103.0 - - Probable R
SH1S Pukapuka Stream - Realignment Design 5 MMH Cat2 324 100% 80.0 - 80.0 - Probable R
SH6 Battys Road I/S Investigation 14 MMH Cat2 324 100% 13.0 - - 13.0 Probable R
Sneiders Creek Realignment Construction 2 MMH Cat2 324 100% 1,783.0 - 874.0 909.0 Probable R
Improved Driver Information 9/12 Construction 30 MMM Cat2 321 100% 157.4 50.9 52.5 54.0 Probable R/N
Marlborough Region PL Investigation 18 MMM Cat2 324 100% 124.0 124.0 - - Probable R/N
Marlborough Region PL Design 18 MMM Cat2 324 100% 127.0 - 127.0 - Probable R/N
Marlborough Region PL Construction 18 MMM Cat2 324 100% 765.0 - - 765.0 Probable R/N
Property Acquisitions 9/12 Property 29 MMM Cat2 331 100% 541.9 175.3 180.6 186.0 Probable R/N
Rehabilitation Seal Widening 9/12 Construction 1 MMM Cat2 324 100% 196.8 63.7 65.6 67.5 Probable R/N
Safety Retrofit 9/12 Construction 1 MMM Cat2 324 100% 590.3 191.0 196.7 202.6 Probable R/N
Seismic Retrofit 9/12 Construction 19 MMM Cat2 322 100% 836.0 - 60.0 776.0 Probable R/N
SH1 Mirza Bridge Widening Investigation 25 MMM Cat2 322 100% 43.7 - - 43.7 Probable R/N
SH1 Tarbarrel Southbound P/L Investigation 24 MMM Cat2 324 100% 87.0 - - 87.0 Probable R/N
SH1S Dazzle Corner - Realignment Investigation 6 MMM Cat2 324 100% 170.0 170.0 - - Probable R/N
SH1S Dazzle Corner - Realignment Design 6 MMM Cat2 324 100% 175.0 - 175.0 - Probable R/N
SH6 Bells Road / St Leonards Road I/S Investigation 17 MMM Cat2 324 100% 57.0 57.0 - - Probable R/N
SH6 Colemans I/S Design 13 MMM Cat2 324 100% 36.0 36.0 - - Probable R/N
SH6 Rai Saddle Southside Curve Realignment - Sec C Investigation 22 MMM Cat2 324 100% 164.7 - 42.4 122.3 Probable R/N
Strategic Plan Initiatives 9/12 Construction 27 MMM Cat2 324 100% 472.2 152.8 157.4 162.1 Probable R/N
SH1 / Alabama Road Intersection Improvements Investigation 15 MML Cat2 324 100% 66.0 - - 66.0 Possible N
SH1 Ross Lane I/S Investigation 23 MML Cat2 323 100% 76.5 - - 76.5 Possible N
SH62 Rapaura - Wratts to SH1 Construction 16 MML Cat2 324 100% 3.2 2.3 0.9 - Possible N
SH63 Eves Bridge 2L Investigation 31 MML Cat2 322 100% 65.6 - - 65.6 Possible N
SH63 Renwick Back Road - Seal Widening Investigation 26 MML Cat2 324 100% 54.6 - - 54.6 Possible N
Demand management & community programmes
Community Advertising 9/12 - Marlborough Implementation App. 432 100% - 13.2 - - N
Walking and cycling facilities
Walking and Cycling - Access and community benefits Group allocation Alloc. - - -
SH1 Spring Creek to Blenheim Cycle Improvements Investigation 8 LMM Reserve 452 100% 50.0 50.0 - - Res. A
SH1 Spring Creek to Blenheim Cycle Improvements Design 8 LMM Reserve 452 100% 51.5 - 51.5 - Res. A
SH1 Spring Creek to Blenheim Cycle Improvements Construction 8 LMM Reserve 452 100% 1,103.3 - - 1,103.3 Res. A
SH1 Blenheim to Riverlands Cycle Improvements Investigation 7 LMM Reserve 452 100% 50.0 50.0 - - Res. A
SH1 Blenheim to Riverlands Cycle Improvements Design 7 LMM Reserve 452 100% 30.9 - 30.9 - Res. A
SH1 Blenheim to Riverlands Cycle Improvements Construction 7 LMM Reserve 452 100% 742.6 - - 742.6 Res. A
Transport planning
Activity management plans Study Cat2 003 100% 287.4 93.1 97.1 97.1 N
Marlborough Safe, sustainable and Efficient Routes Study 1 MM_ Cat2 002 100% 100.0 34.0 33.0 33.0 N