Phase |
Regional priority |
Profile |
Status |
Work category |
Indicative FAR* |
Total phase cost |
2009/10 NLTF ($000) |
2010/11 NLTF ($000) |
2011/12 NLTF ($000) |
Funding priority |
Funding source* |
BOP Highway & Network Operations |
Renewal of state highways |
Road renewals |
State Highways |
|
|
App. |
|
|
65,784.2 |
24,128.0 |
20,828.1 |
20,828.1 |
|
N |
Preventive Maintenance 9/12 |
Construction |
1 |
|
Cat2 |
241 |
100% |
3,262.9 |
1,393.5 |
928.9 |
940.5 |
|
|
Scour Investigation 9/12 |
Construction |
122 |
|
Cat2 |
241 |
100% |
352.0 |
114.0 |
117.0 |
121.0 |
|
|
Operation and maintenance of state highways |
|
|
|
|
|
|
|
|
|
|
|
|
Road operations and maintenance |
State Highways |
|
|
App. |
|
|
66,907.3 |
22,292.6 |
22,307.4 |
22,307.4 |
|
N |
EW (3873 & 3877) Matata & TCC Event BOP R4 18 May 05 |
Construction |
- |
|
Com |
141 |
100% |
- |
996.9 |
- |
- |
|
N |
New & improved infrastructure for State highways |
|
|
|
|
|
|
|
|
|
|
|
|
Hairini Link (Stages 3 and 4) |
Investigation |
9 |
|
Com |
324 |
100% |
2,340.6 |
1,546.1 |
794.6 |
- |
|
R |
Harbour Link |
Construction |
5 |
|
Com |
323 |
100% |
192,099.0 |
20,000.3 |
249.7 |
- |
|
C |
Katikati Bypass |
Investigation |
20 |
|
Com |
324 |
100% |
619.2 |
107.9 |
- |
- |
|
R |
Omokoroa Road intersection improvements |
Investigation |
15 |
|
Com |
323 |
100% |
530.6 |
82.0 |
- |
- |
|
N |
Pyes Pa Bypass |
Construction |
19 |
|
Com |
324 |
100% |
14,339.7 |
9,796.9 |
4,542.8 |
- |
|
R |
Pyes Pa Bypass |
Construction |
19 |
|
Com |
323 |
100% |
8,000.0 |
4,500.0 |
3,500.0 |
- |
|
R |
Tauranga Central Corridor: Hairini Link Adv Works (Stage 2) |
Design |
23 |
|
Com |
324 |
100% |
506.1 |
312.1 |
- |
- |
|
N |
Tauranga Eastern Link |
Design |
6 |
|
Com |
324 |
100% |
2,500.0 |
2,500.0 |
- |
- |
|
R |
Tauranga Eastern Link |
Property |
6 |
|
Com |
331 |
100% |
51,985.8 |
35,305.1 |
16,680.8 |
- |
|
R & N |
Tauranga Northern Link |
Investigation |
8 |
|
Com |
324 |
100% |
3,100.0 |
1,554.2 |
1,545.8 |
- |
|
R |
Waitahanui Bridge Replacement. |
Design |
- |
|
Com |
322 |
100% |
377.7 |
- |
159.6 |
218.0 |
|
N |
Apirana Curves Realignment |
Investigation |
|
|
Com |
|
100% |
104.2 |
42.4 |
- |
- |
|
N |
Awaiti Intersection Improvements |
Investigation |
|
|
Com |
|
100% |
105.0 |
59.9 |
- |
- |
|
N |
Banksia Rd PL |
Investigation |
|
|
Com |
|
100% |
83.6 |
42.4 |
- |
- |
|
N |
Fairy Springs 4L Stage 2 |
Construction |
|
|
Com |
|
100% |
4,295.0 |
2,255.0 |
2,040.0 |
- |
|
N |
Five Mile Gate PL |
Investigation |
|
|
Com |
|
100% |
100.0 |
70.0 |
- |
- |
|
N |
Mangorewa Stream North & South Bridge Widening |
Construction |
|
|
Com |
|
100% |
4,259.0 |
2,000.0 |
1,289.0 |
- |
|
N |
Soldiers Road Realignment + IS |
Investigation |
|
|
Com |
|
100% |
200.1 |
60.8 |
- |
- |
|
N |
Sun Valley Realignment |
Investigation |
|
|
Com |
|
100% |
157.3 |
107.3 |
- |
- |
|
N |
Taneatua Rail Overbridge |
Investigation |
|
|
Com |
|
100% |
160.5 |
60.0 |
- |
- |
|
N |
Waipa Curve Realignment |
Investigation |
|
|
Com |
|
100% |
125.1 |
85.1 |
- |
- |
|
N |
Wharawhara Road Roundabout |
Investigation |
|
|
Com |
|
100% |
280.1 |
90.0 |
- |
- |
|
N |
Minor improvements 2009/12 |
State Highways |
|
|
App. |
341 |
|
- |
2,998.2 |
2,958.0 |
2,958.0 |
|
N |
Bethlehem to Route J - Four laning (SH2) |
Design |
|
MMH |
Cat2 |
323 |
100% |
636.5 |
- |
636.5 |
- |
Probable |
R/N |
Bethlehem to Route J - Four laning (SH2) |
Investigation |
14 |
MMH |
Cat2 |
323 |
100% |
412.0 |
412.0 |
- |
- |
Probable |
R/N |
Bethlehem to Route J - Four laning (SH2) |
Property |
|
MMH |
Cat2 |
323 |
100% |
2,200.8 |
- |
468.6 |
731.9 |
Probable |
R/N |
Reids Canal Bridge Replacement (Large Project) |
Construction |
11 |
MMH |
Cat2 |
322 |
100% |
6,069.7 |
- |
182.0 |
5,565.3 |
Probable |
R/N |
Reids Canal Bridge Replacement (Large Project) |
Design |
11 |
MMH |
Cat2 |
322 |
100% |
468.1 |
309.2 |
158.9 |
- |
Probable |
R/N |
Reids Canal Bridge Replacement (Large Project) |
Property |
|
MMH |
Cat2 |
322 |
100% |
51.5 |
51.5 |
- |
- |
Probable |
R/N |
Tauranga Central Corridor: Hairini Link Adv Works (Stage 2) |
Construction |
23 |
MMH |
Cat2 |
324 |
100% |
5,965.0 |
1,163.0 |
3,891.0 |
911.0 |
Probable |
R/N |
Tauranga Eastern Link |
Construction |
6 |
HHL |
Cat2 |
324 |
100% |
469,050.7 |
- |
- |
54,995.8 |
Probable |
C/N |
Tauranga Eastern Link |
Construction |
|
HHL |
Cat2 |
|
|
31,517.2 |
10,328.3 |
21,188.9 |
- |
Probable |
R |
Katikati Bypass |
Design |
|
MMM |
Cat2 |
324 |
100% |
2,169.5 |
- |
530.5 |
1,639.1 |
Probable |
R/N |
Katikati Bypass |
Property |
|
MMM |
Cat2 |
324 |
100% |
5,033.6 |
- |
526.1 |
1,094.7 |
Probable |
R/N |
Omokoroa Road intersection improvements |
Design |
|
MMM |
Cat2 |
323 |
100% |
318.3 |
- |
318.3 |
- |
Probable |
R/N |
Tauriko Bypass |
Design |
21 |
MMM |
Cat2 |
323 |
100% |
2,060.0 |
2,060.0 |
- |
- |
Probable |
R/N |
Waitahanui Bridge Replacement. |
Property |
|
MMM |
Cat2 |
322 |
100% |
401.3 |
- |
- |
132.3 |
Probable |
R/N |
Hairini Link (Stages 3 and 4) |
Property |
9 |
MLL |
Reserve |
331 |
100% |
1,688.8 |
- |
- |
544.0 |
Res. A |
|
Rotorua Eastern Arterial |
Investigation |
7 |
LML |
Reserve |
323 |
100% |
2,083.0 |
1,292.5 |
790.6 |
- |
Res. A |
|
Strategic network group |
Group allocation |
|
|
Alloc. |
|
|
|
2,437.5 |
2,681.3 |
2,681.3 |
|
|
Soldiers Road Realignment + IS |
Design |
30 |
HMH |
Cat2 |
324 |
100% |
150.0 |
120.0 |
30.0 |
- |
Probable |
R |
Soldiers Road Realignment + IS |
Construction |
30 |
HMH |
Cat2 |
324 |
100% |
4,500.0 |
- |
- |
2,500.0 |
Probable |
R |
Kaimais SI - SH29 NSC |
Investigation |
52 |
HMM |
Cat2 |
324 |
100% |
156.0 |
77.0 |
79.0 |
- |
Probable |
R/N |
Kaimais SI - SH29 NSC |
Design |
52 |
HMM |
Cat2 |
324 |
100% |
66.0 |
- |
66.0 |
- |
Probable |
R/N |
Kaimais SI - SH29 NSC |
Construction |
52 |
HMM |
Cat2 |
324 |
100% |
3,000.0 |
- |
1,500.0 |
1,500.0 |
Probable |
R/N |
Kaimais SI - SH29 NSC Stage 2 |
Investigation |
52 |
HMM |
Cat2 |
324 |
100% |
82.0 |
- |
- |
82.0 |
Probable |
R/N |
Maunganui Rd/Girven Rd Roundabout Signalisation |
Investigation |
- |
HMM |
Cat2 |
324 |
100% |
0.1 |
0.1 |
- |
- |
Probable |
R |
Maunganui Rd/Girven Rd Roundabout Signalisation |
Design |
- |
HMM |
Cat2 |
324 |
100% |
0.2 |
0.2 |
- |
- |
Probable |
R |
Maunganui Rd/Girven Rd Roundabout Signalisation |
Construction |
- |
HMM |
Cat2 |
324 |
100% |
1.5 |
- |
1.5 |
- |
Probable |
R |
Redwood-Omanawa Road Realignment |
Investigation |
51 |
HMM |
Cat2 |
324 |
100% |
200.0 |
200.0 |
- |
- |
Probable |
R/N |
Redwood-Omanawa Road Realignment |
Design |
51 |
HMM |
Cat2 |
324 |
100% |
250.0 |
- |
250.0 |
- |
Probable |
R/N |
Redwood-Omanawa Road Realignment |
Construction |
51 |
HMM |
Cat2 |
324 |
100% |
4,500.0 |
- |
- |
2,000.0 |
Probable |
R/N |
Sun Valley Realignment |
Design |
108 |
HMM |
Cat2 |
324 |
100% |
85.0 |
- |
85.0 |
- |
Probable |
R/N |
Tauranga Signage Upgrade (SH2/29) |
Design |
132 |
HMM |
Cat2 |
324 |
100% |
52.0 |
52.0 |
- |
- |
Probable |
R |
Maketu Road I/S Improvement Te Puke |
Investigation |
93 |
HHL |
Cat2 |
324 |
100% |
108.0 |
- |
53.0 |
55.0 |
Probable |
N |
Pah Road I/S Improvement Te Puke |
Investigation |
94 |
HHL |
Cat2 |
324 |
100% |
55.0 |
- |
- |
55.0 |
Probable |
N |
Improve, expand or replace network group |
Group allocation |
|
|
Alloc. |
|
|
|
5,531.3 |
6,084.4 |
6,084.4 |
|
|
Arden Cottage Curves Realignment |
Investigation |
26 |
MMH |
Cat2 |
324 |
100% |
140.0 |
80.0 |
60.0 |
- |
Probable |
R/N |
Arden Cottage Curves Realignment |
Design |
26 |
MMH |
Cat2 |
324 |
100% |
165.0 |
- |
- |
165.0 |
Probable |
R/N |
Banksia Rd PL |
Design |
27 |
MMH |
Cat2 |
324 |
100% |
53.0 |
- |
53.0 |
- |
Probable |
R/N |
Bethlehem Township Four-Laning |
Design |
58 |
MMH |
Cat2 |
324 |
100% |
52.0 |
52.0 |
- |
- |
Probable |
R/N |
Bethlehem Township Four-Laning |
Construction |
58 |
MMH |
Cat2 |
324 |
100% |
2,300.0 |
- |
1,500.0 |
800.0 |
Probable |
R/N |
Five Mile Gate PL |
Design |
57 |
MMH |
Cat2 |
324 |
100% |
52.0 |
52.0 |
- |
- |
Probable |
R/N |
Five Mile Gate PL |
Construction |
57 |
MMH |
Cat2 |
324 |
100% |
665.0 |
- |
- |
329.0 |
Probable |
R/N |
Forest Passing Lane (SH33) |
Investigation |
59 |
MMH |
Cat2 |
324 |
100% |
82.0 |
82.0 |
- |
- |
Probable |
R/N |
Forest Passing Lane (SH33) |
Design |
59 |
MMH |
Cat2 |
324 |
100% |
64.0 |
- |
64.0 |
- |
Probable |
R/N |
Mangapouri Bridge Widening |
Design |
29 |
MMH |
Cat2 |
322 |
100% |
36.0 |
36.0 |
- |
- |
Probable |
R/N |
Mangapouri Bridge Widening |
Construction |
29 |
MMH |
Cat2 |
322 |
100% |
1,292.0 |
- |
637.0 |
655.0 |
Probable |
R/N |
Ngongotaha BP Service Station Curve Realignment |
Investigation |
60 |
MMH |
Cat2 |
324 |
100% |
55.0 |
- |
- |
55.0 |
Probable |
R/N |
Pekatahi Road/Rail Bridge Upgrade |
Investigation |
55 |
MMH |
Cat2 |
322 |
100% |
152.0 |
52.0 |
100.0 |
- |
Probable |
R/N |
Pekatahi Road/Rail Bridge Upgrade |
Design |
55 |
MMH |
Cat2 |
322 |
100% |
164.0 |
- |
64.0 |
100.0 |
Probable |
R/N |
Pekatahi Road/Rail Bridge Upgrade |
Construction |
55 |
MMH |
Cat2 |
322 |
100% |
1,375.0 |
- |
- |
680.0 |
Probable |
R/N |
Rotoma Hills PL |
Investigation |
134 |
MMH |
Cat2 |
324 |
100% |
84.9 |
- |
84.9 |
- |
Probable |
R/N |
Rotoma Hills PL |
Design |
134 |
MMH |
Cat2 |
324 |
100% |
65.6 |
- |
- |
65.6 |
Probable |
R/N |
Rotoma Hills SVB |
Investigation |
135 |
MMH |
Cat2 |
324 |
100% |
76.5 |
- |
- |
76.5 |
Probable |
R/N |
SH29 SEDF |
Investigation |
56 |
MMH |
Cat2 |
321 |
100% |
50.0 |
50.0 |
- |
- |
Probable |
R/N |
SH29 SEDF |
Construction |
56 |
MMH |
Cat2 |
321 |
100% |
600.0 |
- |
- |
600.0 |
Probable |
R/N |
Taneatua Rail Overbridge |
Design |
25 |
MMH |
Cat2 |
322 |
100% |
64.0 |
64.0 |
- |
- |
Probable |
R/N |
Taneatua Rail Overbridge |
Construction |
25 |
MMH |
Cat2 |
322 |
100% |
576.0 |
- |
576.0 |
- |
Probable |
R/N |
Waipa Curve Realignment |
Design |
28 |
MMH |
Cat2 |
324 |
100% |
86.0 |
- |
42.0 |
44.0 |
Probable |
R/N |
Apirana Curves Realignment |
Design |
50 |
MMM |
Cat2 |
324 |
100% |
74.0 |
- |
74.0 |
- |
Probable |
N |
Improved Driver Information 9/12 |
Construction |
110 |
MMM |
Cat2 |
321 |
100% |
1,246.1 |
403.2 |
415.2 |
427.7 |
Probable |
R/N |
Kopuroa PL |
Investigation |
48 |
MMM |
Cat2 |
324 |
100% |
87.0 |
- |
- |
87.0 |
Probable |
N |
Maraeroa PL |
Design |
124 |
MMM |
Cat2 |
324 |
100% |
64.0 |
32.0 |
32.0 |
- |
Probable |
N |
Maraeroa PL |
Construction |
124 |
MMM |
Cat2 |
324 |
100% |
1,650.0 |
- |
- |
1,650.0 |
Probable |
N |
Ngongotaha RAB Tidal Improvements (Lights) |
Design |
- |
MMM |
Cat2 |
321 |
100% |
21.0 |
21.0 |
- |
- |
Probable |
N |
Ngongotaha RAB Tidal Improvements (Lights) |
Construction |
- |
MMM |
Cat2 |
321 |
100% |
130.0 |
130.0 |
- |
- |
Probable |
N |
Pavement Smoothing 9/12 |
Construction |
131 |
MMM |
Cat2 |
324 |
100% |
2,200.0 |
505.0 |
726.2 |
968.8 |
Probable |
R/N |
Property Acquisitions 9/12 |
Property |
104 |
MMM |
Cat2 |
331 |
100% |
1,950.0 |
600.0 |
650.0 |
700.0 |
Probable |
R/N |
Rehabilitation Seal Widening 9/12 |
Construction |
105 |
MMM |
Cat2 |
324 |
100% |
1,557.6 |
503.9 |
519.1 |
534.6 |
Probable |
R/N |
Rotorua Weighpit Facilities (SH33/36) |
Investigation |
109 |
MMM |
Cat2 |
321 |
100% |
31.0 |
31.0 |
- |
- |
Probable |
R/N |
Rotorua Weighpit Facilities (SH33/36) |
Design |
109 |
MMM |
Cat2 |
321 |
100% |
32.0 |
- |
32.0 |
- |
Probable |
R/N |
Rotorua Weighpit Facilities (SH33/36) |
Construction |
109 |
MMM |
Cat2 |
321 |
100% |
513.0 |
250.0 |
- |
263.0 |
Probable |
R/N |
Safety Retrofit 9/12 |
Construction |
4 |
MMM |
Cat2 |
324 |
100% |
3,069.0 |
1,511.8 |
1,557.2 |
- |
Probable |
R/N |
Seismic Retrofit 9/12 |
Construction |
113 |
MMM |
Cat2 |
324 |
100% |
1,494.0 |
1,444.0 |
- |
50.0 |
Probable |
R/N |
SH2 Katikati Urban SI |
Investigation |
107 |
MMM |
Cat2 |
324 |
100% |
41.0 |
41.0 |
- |
- |
Probable |
N |
SH2 Katikati Urban SI |
Design |
107 |
MMM |
Cat2 |
324 |
100% |
42.0 |
42.0 |
- |
- |
Probable |
N |
SH2 Katikati Urban SI |
Construction |
107 |
MMM |
Cat2 |
324 |
100% |
760.0 |
- |
760.0 |
- |
Probable |
N |
SH29 SEDF |
Design |
56 |
MMM |
Cat2 |
321 |
100% |
20.0 |
- |
20.0 |
- |
Probable |
R/N |
Strategic Plan Initiatives 9/12 |
Construction |
121 |
MMM |
Cat2 |
321 |
100% |
738.3 |
209.5 |
245.7 |
283.1 |
Probable |
R/N |
Waitahanui Realignment |
Design |
17 |
MMM |
Cat2 |
324 |
100% |
106.1 |
- |
106.1 |
- |
Probable |
R/N |
Wharawhara Road Roundabout |
Design |
123 |
MMM |
Cat2 |
324 |
100% |
108.0 |
- |
53.0 |
55.0 |
Probable |
N |
Bridgeman Lane PL |
Investigation |
127 |
MML |
Cat2 |
324 |
100% |
66.0 |
66.0 |
- |
- |
Possible |
N |
Bridgeman Lane PL |
Design |
127 |
MML |
Cat2 |
324 |
100% |
63.0 |
21.0 |
42.0 |
- |
Possible |
N |
Kauri Point PL |
Design |
130 |
MML |
Cat2 |
324 |
100% |
94.0 |
41.0 |
53.0 |
- |
Possible |
N |
Kauri Point PL |
Construction |
130 |
MML |
Cat2 |
324 |
100% |
2,500.0 |
- |
- |
1,500.0 |
Possible |
N |
Marshall Street Signalisation |
Design |
129 |
MML |
Cat2 |
324 |
100% |
72.0 |
- |
- |
72.0 |
Possible |
N |
Response to Development - BOP |
Investigation |
111 |
MML |
Cat2 |
321 |
100% |
103.0 |
103.0 |
- |
- |
Possible |
N |
Response to Development - BOP |
Design |
111 |
MML |
Cat2 |
321 |
100% |
106.0 |
- |
106.0 |
- |
Possible |
N |
Response to Development - BOP |
Construction |
111 |
MML |
Cat2 |
321 |
100% |
1,500.0 |
- |
- |
500.0 |
Possible |
N |
SH30/33 Intersection |
Investigation |
92 |
MML |
Cat2 |
324 |
100% |
162.0 |
- |
80.0 |
82.0 |
Possible |
N |
Tuapiro Rd PL |
Design |
126 |
MML |
Cat2 |
324 |
100% |
100.0 |
- |
100.0 |
- |
Possible |
N |
Worlsley Rd PL |
Investigation |
128 |
MML |
Cat2 |
324 |
100% |
88.0 |
88.0 |
- |
- |
Possible |
N |
Worlsley Rd PL |
Design |
128 |
MML |
Cat2 |
324 |
100% |
63.0 |
21.0 |
42.0 |
- |
Possible |
N |
Bethlehem to Route J - Four laning (SH2) |
Construction |
|
|
Reserve |
|
|
18,632.5 |
|
|
|
Res. B |
|
Maunganui Rd/Girven Rd I/S |
Construction |
13 |
|
Reserve |
|
|
17,416.0 |
|
|
|
Res. B |
|
Maunganui Rd/Girven Rd I/S |
Design |
13 |
|
Reserve |
|
|
605.0 |
|
|
|
Res. B |
|
Maunganui Rd/Girven Rd I/S |
Investigation |
13 |
|
Reserve |
|
|
587.0 |
|
|
|
Res. B |
|
Rotorua Eastern Arterial |
Design |
7 |
|
Reserve |
|
|
3,517.2 |
|
|
|
Res. B |
|
Rotorua Eastern Arterial |
Property |
7 |
|
Reserve |
|
|
9,167.0 |
|
|
|
Res. B |
|
Tauranga Northern Link |
Design |
8 |
|
Reserve |
|
|
7,203.0 |
|
|
|
Res. B |
|
Hemo Rd / Old Taupo Rd Intersection |
Investigation |
- |
|
N/F |
|
|
|
|
|
|
|
|
Public transport infrastructure |
Tauranga Central Corridor Improvements Stage 4 |
Design |
- |
|
N/F |
|
|
|
|
|
|
|
|
Tauranga Central Corridor Improvements Stage 4 |
Investigation |
- |
|
N/F |
|
|
|
|
|
|
|
|
Demand management & community programmes |
|
|
|
|
|
|
|
|
|
|
|
|
Community Advertising 9/12 - Bay of Plenty |
Implementation |
|
|
App. |
432 |
100% |
- |
44.0 |
- |
- |
|
N |
Walking and cycling facilities |
Poike Road Pedestrian & Cycle Facility |
Investigation |
125 |
|
Com |
452 |
100% |
30.0 |
20.0 |
- |
- |
|
N |
Walking and Cycling - Key safety and congestion |
Group allocation |
|
|
Alloc. |
|
|
|
151.8 |
151.8 |
151.8 |
|
|
Te Maunga Pedestrian Strategy Link |
Design |
53 |
MMM |
Cat2 |
451 |
100% |
55.0 |
55.0 |
- |
- |
Possible |
R/N |
Te Maunga Pedestrian Strategy Link |
Construction |
53 |
MMM |
Cat2 |
452 |
100% |
318.3 |
- |
318.3 |
- |
Possible |
R/N |
Wairoa Bridge Ped/Cycle SI |
Investigation |
54 |
MMM |
Cat2 |
452 |
100% |
20.0 |
20.0 |
- |
- |
Possible |
R/N |
Wairoa Bridge Ped/Cycle SI |
Design |
54 |
MMM |
Cat2 |
452 |
100% |
45.0 |
35.0 |
10.0 |
- |
Possible |
R/N |
Wairoa Bridge Ped/Cycle SI |
Construction |
54 |
MMM |
Cat2 |
452 |
100% |
700.0 |
- |
500.0 |
200.0 |
Possible |
R/N |
Walking and Cycling - Access and community benefits |
Group allocation |
|
|
Alloc. |
|
|
|
- |
- |
- |
|
|
Mourea Bridge Pedestrian Cycleway |
Investigation |
98 |
LMM |
Reserve |
452 |
100% |
50.0 |
40.0 |
- |
- |
Res. A |
|
Mourea Bridge Pedestrian Cycleway |
Design |
98 |
LMM |
Reserve |
452 |
100% |
50.0 |
20.0 |
30.0 |
- |
Res. A |
|
Mourea Bridge Pedestrian Cycleway |
Construction |
98 |
LMM |
Reserve |
452 |
100% |
821.0 |
- |
- |
821.0 |
Res. A |
|
Transport planning |
BOP Regional SH Strategy |
Study |
|
|
Com |
002 |
100% |
140.0 |
44.4 |
- |
- |
|
N |
Eastern Bay of Plenty Route Security Study |
Study |
|
|
Com |
002 |
100% |
250.0 |
246.4 |
- |
- |
|
N |
Omokoroa Park and Ride Study |
Study |
|
|
Com |
002 |
100% |
25.0 |
5.1 |
- |
- |
|
N |
Rotorua Central Strategic Study |
Study |
|
|
Com |
002 |
100% |
250.0 |
53.1 |
- |
- |
|
N |
Tauranga Northern Corridor Strategic Study |
Study |
|
|
Com |
002 |
100% |
547.1 |
45.9 |
- |
- |
|
N |
Tauranga South-Western Corridor Strategic Study |
Study |
|
|
Com |
002 |
100% |
235.9 |
145.2 |
- |
- |
|
N |
Activity management plans |
Study |
|
|
Cat2 |
003 |
100% |
2,198.3 |
739.2 |
729.5 |
729.5 |
|
N |
BoP Interregional freight and passenger route study |
Study |
33 |
HM_ |
Cat2 |
002 |
100% |
100.0 |
100.0 |
- |
- |
|
N |
BoP Kiwirap Black Routes Safety Study |
Study |
35 |
MM_ |
Cat2 |
002 |
100% |
100.0 |
100.0 |
- |
- |
|
N |
BOP Passing Opportunties |
Study |
41 |
MM_ |
Cat2 |
002 |
100% |
250.0 |
- |
100.0 |
150.0 |
|
N |
BoP Regional Transportation Study |
Study |
44 |
MM_ |
Cat2 |
002 |
100% |
400.0 |
100.0 |
200.0 |
100.0 |
|
N |
BoP Strategic Walking and Cycling Study |
Study |
36 |
MM_ |
Cat2 |
002 |
100% |
80.4 |
- |
53.0 |
27.3 |
|
N |
Central Tauranga Roading Improvements |
Study |
37 |
MH_ |
Cat2 |
002 |
100% |
100.0 |
- |
100.0 |
- |
|
N |
Eastern BoP Network Form |
Study |
45 |
MM_ |
Cat2 |
002 |
100% |
54.6 |
- |
- |
54.6 |
|
N |
Greater Rotorua (SH 5,30,30a,33,36) Strategic Study |
Study |
40 |
MH_ |
Cat2 |
002 |
100% |
209.1 |
103.0 |
106.1 |
- |
|
N |
Greater Tauranga (SH 2/29/36) Strategic Study |
Study |
32 |
HH_ |
Cat2 |
002 |
100% |
213.8 |
- |
159.1 |
54.6 |
|
N |
Kaimai to Tauranga (SH29) Strategic Study |
Study |
34 |
HH_ |
Cat2 |
002 |
100% |
209.1 |
103.0 |
106.1 |
- |
|
N |
Safe and Sustainable Freight Access |
Study |
39 |
HM_ |
Cat2 |
002 |
100% |
100.0 |
- |
- |
100.0 |
|
N |
State Highway Optimisation Strategies |
Study |
46 |
ML_ |
Cat2 |
002 |
100% |
106.1 |
34.3 |
35.4 |
36.4 |
|
N |
Twin City Link Function and Form Study |
Study |
47 |
MM_ |
Cat2 |
002 |
100% |
79.6 |
- |
79.6 |
- |
|
N |
Waihi to Tauranga (SH2) Strategic Study |
Study |
43 |
MH_ |
Cat2 |
002 |
100% |
150.0 |
- |
100.0 |
50.0 |
|
N |
BoP PT and Modal Shift (Rural Bus Facilities) Strategy |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
BoP State Highway Activity Management Plan review |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
Environment Bay of Plenty |
Public transport services |
Bus & ferry concession fares |
Operations |
|
|
App. |
513 |
50% |
154.5 |
25.0 |
25.8 |
26.4 |
|
N |
Bus services |
Operations |
|
|
App. |
511 |
50% |
22,431.4 |
3,738.6 |
3,738.6 |
3,738.6 |
|
N |
Public transport facilities maintenance and operations |
Operations |
|
|
App. |
514 |
60% |
2,434.5 |
493.2 |
474.3 |
493.2 |
|
N |
Public transport professional services/ administration |
Operations |
|
|
App. |
|
50% |
1,369.2 |
228.2 |
228.2 |
228.2 |
|
N |
Total mobility flat payments |
Operations |
|
|
App. |
521 |
100% |
277.4 |
92.5 |
92.5 |
92.5 |
|
N |
Total mobility operations |
Operations |
|
|
App. |
517 |
50% |
1,490.0 |
240.0 |
250.0 |
255.0 |
|
N |
Wheelchair hoists |
Operations |
|
|
App. |
519 |
60% |
110.0 |
21.0 |
21.0 |
24.0 |
|
N |
EBOP Improved Public Transport |
Implementation |
10 |
MMM |
Cat2 |
511 |
50% |
- |
194.1 |
936.2 |
1,877.5 |
Possible |
N |
EBOP Improved Public Transport |
Implementation |
10 |
MMM |
Cat2 |
514 |
60% |
- |
7.8 |
- |
2.4 |
Possible |
N |
Demand management & community programmes |
EBOP Regional Community Programmes 2009/12 |
Implementation |
|
|
App. |
432 |
75% |
- |
139.7 |
- |
- |
|
N |
Transport planning |
Public Transport - Bay of Plenty Stocktake |
Study |
- |
|
Com |
002 |
75% |
65.0 |
41.3 |
- |
- |
|
N |
Regional land transport planning management |
Implementation |
|
|
App. |
001 |
100% |
775.2 |
266.5 |
254.5 |
254.2 |
|
|
Review of National and International PT and Best Practice |
Study |
88 |
HH_ |
App. |
002 |
75% |
35.0 |
22.5 |
- |
- |
|
N |
EBOP Ageing Population study |
Study |
82 |
MM_ |
Cat2 |
002 |
75% |
15.0 |
11.3 |
- |
- |
|
N |
EBOP Alternative Tauranga Harbour rail crossing |
Study |
74 |
LL_ |
Cat2 |
002 |
75% |
35.0 |
26.3 |
- |
- |
|
N |
EBOP Eastern Bay rail corridors |
Study |
77 |
LL_ |
Cat2 |
002 |
75% |
20.0 |
- |
15.0 |
- |
|
N |
EBOP Forestry Roads Study |
Study |
85 |
MM_ |
Cat2 |
002 |
75% |
50.0 |
- |
- |
37.5 |
|
N |
EBOP Impacts of Regional Growth on Transport Study |
Study |
86 |
MM_ |
Cat2 |
002 |
75% |
80.0 |
60.0 |
- |
- |
|
N |
EBOP Reduce Noise and Vibration study |
Study |
69 |
MM_ |
Cat2 |
002 |
75% |
25.0 |
18.8 |
- |
- |
|
N |
EBOP Regional Freight Study |
Study |
62 |
HM_ |
Cat2 |
002 |
75% |
100.0 |
75.0 |
- |
- |
|
N |
EBOP Regional Walking and Cycling Network Planning |
Study |
89 |
MM_ |
Cat2 |
002 |
75% |
70.0 |
26.3 |
26.3 |
- |
|
N |
EBOP RLTS Monitoring Framework |
Study |
91 |
HM_ |
Cat2 |
002 |
75% |
40.0 |
15.0 |
7.5 |
7.5 |
|
N |
EBOP RPTP Review |
Study |
68 |
MH_ |
Cat2 |
003 |
60% |
200.0 |
60.0 |
- |
- |
|
N |
EBOP Alternative Waikato rail link |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
EBOP Public Health Access Study |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
EBOP Rail electrification investigation |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
EBOP Relationship Transport Improvements & Economic Develpmt |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
EBOP RLTS Implementation |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
EBOP Sub standard transportation networks study |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
Supergold card |
Supergold trip adminstration |
Implementation |
|
|
App. |
|
|
30.0 |
10.0 |
10.0 |
10.0 |
|
|
Supergold trip payments |
Implementation |
|
|
App. |
|
|
980.0 |
320.0 |
330.0 |
330.0 |
|
|
Kawerau District Council |
Renewal of local roads |
Road renewals |
Local Roads |
|
|
App. |
|
|
638.0 |
142.0 |
144.7 |
140.7 |
|
N |
Operation and maintenance of local roads |
Road operations and maintenance |
Local Roads |
|
|
App. |
|
|
719.3 |
169.1 |
154.0 |
158.8 |
|
N |
New & improved infrastructure for local roads |
Minor improvements 2009/12 |
Local Roads |
|
|
App. |
341 |
|
- |
24.9 |
21.3 |
21.0 |
|
N |
Opotiki District Council |
Renewal of local roads |
Road renewals |
Local Roads |
|
|
App. |
|
|
2,022.0 |
334.1 |
345.8 |
351.3 |
|
N |
Operation and maintenance of local roads |
Road operations and maintenance |
Local Roads |
|
|
App. |
|
|
4,010.1 |
661.6 |
688.2 |
695.4 |
|
N |
Amokura Road Washout Flood Damage |
Construction |
- |
|
Com |
141 |
52% |
- |
49.4 |
- |
- |
|
N |
New & improved infrastructure for local roads |
Minor improvements 2009/12 |
Local Roads |
|
|
App. |
341 |
|
- |
79.6 |
73.6 |
73.4 |
|
N |
User benefits improvements group |
Group allocation |
|
|
Alloc. |
|
|
|
100.0 |
100.0 |
100.0 |
|
|
Papanui Road Seal Extension |
Construction |
- |
LML |
Reserve |
325 |
61% |
120.0 |
73.2 |
- |
- |
Res. A |
|
Walking and cycling facilities |
Walking and Cycling - Access and community benefits |
Group allocation |
|
|
Alloc. |
|
|
|
- |
- |
- |
|
|
Transport planning |
Transport Planning 002 Opotiki Harbour Development |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
Rotorua District Council |
Renewal of local roads |
Road renewals |
Local Roads |
|
|
App. |
|
|
14,013.3 |
2,146.8 |
2,146.4 |
2,152.9 |
|
N |
Operation and maintenance of local roads |
Road operations and maintenance |
Local Roads |
|
|
App. |
|
|
13,836.8 |
2,082.9 |
2,127.4 |
2,162.7 |
|
N |
New & improved infrastructure for local roads |
Malfroy/Ranolf Roundabout |
Construction |
- |
|
Com |
324 |
56% |
1,333.0 |
280.0 |
- |
- |
|
N |
Minor improvements 2009/12 |
Local Roads |
|
|
App. |
341 |
|
- |
338.4 |
304.2 |
302.6 |
|
N |
Lake Rd 4-Laning |
Design |
12 |
MMH |
Cat2 |
324 |
56% |
7,342.4 |
90.7 |
4,021.0 |
- |
Probable |
R/N |
Public transport infrastructure |
Rotorua Transportation Centre |
Design |
49 |
MMM |
Cat2 |
531 |
60% |
3,271.0 |
150.0 |
1,200.0 |
612.6 |
Possible |
N |
Demand management & community programmes |
Road Safety & Sustainability Projects 2009/12 |
Implementation |
|
|
App. |
432 |
75% |
- |
218.9 |
- |
- |
|
N |
Rotorua District Traffic Demand Management |
Implementation |
|
|
Cat2 |
432 |
75% |
- |
24.6 |
- |
- |
|
N |
Walking and cycling facilities |
CBD To Ngongotaha Cycling Route |
Construction |
- |
|
Com |
452 |
56% |
900.0 |
84.0 |
84.0 |
84.0 |
|
N |
Walking and Cycling - Access and community benefits |
Group allocation |
|
|
Alloc. |
|
|
|
- |
- |
- |
|
|
Tauranga City Council |
Renewal of local roads |
Road renewals |
Local Roads |
|
|
App. |
|
|
17,103.8 |
2,379.2 |
2,451.0 |
2,524.4 |
|
N |
Operation and maintenance of local roads |
Road operations and maintenance |
Local Roads |
|
|
App. |
|
|
16,912.9 |
2,432.5 |
2,447.9 |
2,455.4 |
|
N |
New & improved infrastructure for local roads |
Pyes Pa Bypass |
Construction |
3 |
|
Com |
323 |
53% |
8,000.0 |
2,385.0 |
1,855.0 |
- |
|
R |
Minor improvements 2009/12 |
Local Roads |
|
|
App. |
341 |
|
- |
384.9 |
348.7 |
349.2 |
|
N |
TCC Tara Rd 4 laning |
Construction |
16 |
MMH |
Cat2 |
324 |
53% |
3,720.0 |
- |
678.3 |
615.0 |
Probable |
R/N |
Improve, expand or replace network group |
Group allocation |
|
|
Alloc. |
|
|
|
- |
400.0 |
- |
|
|
TCC Beaumaris Bvd/Sterling Gate/SH2 Link Road |
Construction |
- |
MMM |
Cat2 |
323 |
53% |
800.0 |
424.0 |
- |
- |
Possible |
N |
Public transport infrastructure |
Urban transport choice, network improvements & safety PT group |
Group allocation |
|
|
Alloc. |
|
|
|
150.0 |
150.0 |
150.0 |
|
|
Tauranga Transport Centre construction |
Construction |
31 |
MMM |
Cat2 |
531 |
60% |
750.0 |
180.0 |
270.0 |
- |
Possible |
N |
Demand management & community programmes |
Tauranga City Community Programmes |
Implementation |
|
|
App. |
432 |
75% |
- |
560.3 |
- |
- |
|
N |
Walking and cycling facilities |
Walking and Cycling - Access and community benefits |
Group allocation |
|
|
Alloc. |
|
|
|
- |
- |
- |
|
|
Transport planning |
Tauranga Central Business District Travel Demand Management |
Study |
71 |
MH_ |
Cat2 |
002 |
75% |
74.2 |
55.7 |
- |
- |
|
N |
TCC Arataki Transport Centre |
Study |
84 |
MM_ |
Cat2 |
002 |
75% |
80.0 |
60.0 |
- |
- |
|
N |
TCC Cameron Rd - Multi Modal Corridor Study |
Study |
79 |
MM_ |
Cat2 |
002 |
75% |
200.0 |
75.0 |
37.5 |
37.5 |
|
N |
TCC Girven Rd Form and Function study |
Study |
72 |
MM_ |
Cat2 |
002 |
75% |
100.0 |
- |
37.5 |
37.5 |
|
N |
TCC Hairini Link Corridor Strategy |
Study |
- |
MM_ |
Cat2 |
002 |
75% |
35.0 |
26.3 |
- |
- |
|
N |
TCC Transport Model Development Planning |
Study |
61 |
HH_ |
Cat2 |
002 |
75% |
70.0 |
37.5 |
15.0 |
- |
|
N |
TCC WELCOME BAY ALTERNATIVE LINK STUDY |
Study |
73 |
MM_ |
Cat2 |
002 |
75% |
50.0 |
37.5 |
- |
- |
|
N |
Western BoP District Council |
Operation and maintenance of local roads |
Road operations and maintenance |
Local Roads |
|
|
App. |
|
|
36,547.9 |
5,473.3 |
5,493.2 |
5,493.2 |
|
N |
Emergency Works 2008 |
Construction |
- |
|
Com |
141 |
45% |
- |
36.0 |
- |
- |
|
N |
New & improved infrastructure for local roads |
Minor improvements 2009/12 |
Local Roads |
|
|
App. |
341 |
|
- |
437.9 |
391.0 |
385.2 |
|
N |
Improve, expand or replace network group |
Group allocation |
|
|
Alloc. |
|
|
|
- |
400.0 |
400.0 |
|
|
Welcome Bay Road Realignment @ 3.92km |
Construction |
- |
MMM |
Cat2 |
324 |
55% |
1,500.0 |
825.0 |
- |
- |
Possible |
R/N |
Demand management & community programmes |
Community programmes |
Implementation |
|
|
N/F |
|
|
|
|
|
|
|
|
Walking and cycling facilities |
Walking and Cycling - Access and community benefits |
Group allocation |
|
|
Alloc. |
|
|
|
- |
- |
- |
|
|
Footpath development |
Construction |
97 |
LML |
Reserve |
451 |
55% |
900.0 |
49.5 |
49.5 |
49.5 |
Res. A |
|
Combined off road walking and cycleway development |
Construction |
97 |
LML |
Reserve |
451 |
55% |
1,000.0 |
55.0 |
55.0 |
55.0 |
Res. A |
|
Transport planning |
Transportation Activity Management Plan - 2009 Update |
Study |
64 |
ML_ |
|
003 |
55% |
1,100.0 |
55.0 |
55.0 |
55.0 |
|
N |
Whakatane District Council |
Renewal of local roads |
Road renewals |
Local Roads |
|
|
App. |
|
|
13,053.0 |
1,536.3 |
2,312.1 |
2,025.5 |
|
N |
Operation and maintenance of local roads |
Road operations and maintenance |
Local Roads |
|
|
App. |
|
|
12,115.5 |
1,745.4 |
1,854.0 |
1,856.2 |
|
N |
WDC Emergency Works Feb/Mar 2009 |
Construction |
- |
|
Com |
141 |
45% |
- |
57.2 |
- |
- |
|
N |
New & improved infrastructure for local roads |
MacDonald Road Pavement Smoothing 08/09 |
Construction |
- |
|
Com |
324 |
55% |
180.8 |
38.5 |
- |
- |
|
N |
Minor improvements 2009/12 |
Local Roads |
|
|
App. |
341 |
|
- |
262.5 |
296.5 |
272.2 |
|
N |
Improve, expand or replace network group |
Group allocation |
|
|
Alloc. |
|
|
|
150.0 |
400.0 |
400.0 |
|
|
Quay St Bridge |
Construction |
- |
MMH |
Cat2 |
322 |
55% |
271.0 |
11.0 |
138.1 |
- |
Probable |
R/N |
Te Kooti Rd Bridge #194 |
Construction |
- |
MMM |
Cat2 |
322 |
55% |
137.0 |
75.4 |
- |
- |
Possible |
R/N |
Matahi Valley Rd Bridge #131 |
Construction |
- |
MMM |
Cat2 |
322 |
55% |
166.0 |
8.8 |
82.5 |
- |
Possible |
R/N |
Luttrells Rd Bridge #126 |
Construction |
- |
MMM |
Cat2 |
322 |
55% |
140.0 |
- |
7.7 |
69.3 |
Possible |
R/N |
Wainui Rd Seal Widening 2010/11 |
Construction |
- |
MMM |
Cat2 |
324 |
55% |
784.0 |
- |
431.2 |
- |
Possible |
N |
Wainui Rd Seal Widening 2011/12 |
Construction |
- |
MMM |
Cat2 |
324 |
55% |
335.0 |
- |
- |
184.3 |
Possible |
R/N |
WDC Thornton Rd Bluberry Curves Realignment 2011/12 |
Investigation |
- |
MMM |
Cat2 |
324 |
55% |
335.0 |
- |
- |
184.3 |
Possible |
N |
WDC Matahi Valley Rd Realignment 2009/10 |
Construction |
- |
MMM |
Cat2 |
324 |
55% |
315.0 |
- |
173.3 |
- |
Possible |
R/N |
WDC Landing Rd RAB 2009/11 |
Design |
- |
MMM |
Cat2 |
324 |
55% |
79.0 |
43.5 |
- |
- |
Possible |
R/N |
WDC Landing Rd RAB 2009/11 |
Construction |
- |
MMM |
Cat2 |
324 |
55% |
759.0 |
- |
417.5 |
- |
Possible |
R/N |
Thornton Rd Seal Widening 2011/12 |
Construction |
- |
MMM |
Cat2 |
324 |
55% |
335.0 |
- |
- |
184.3 |
Possible |
R/N |
WDC Mill Rd to Phoenix Dr Link |
Construction |
- |
MMM |
Cat2 |
323 |
55% |
200.0 |
- |
- |
110.0 |
Possible |
R/N |
User benefits improvements group |
Group allocation |
|
|
Alloc. |
|
|
|
- |
300.0 |
200.0 |
|
|
Ruatahuna Seal Extension 2010/11 |
Construction |
- |
LMH |
Cat2 |
325 |
88% |
326.0 |
- |
285.3 |
- |
Probable |
T |
Ruatahuna Seal Extension 2011/12 |
Construction |
- |
LMH |
Cat2 |
325 |
88% |
336.0 |
- |
17.5 |
276.5 |
Probable |
T |
Ruatahuna Seal Extension 2012/13 |
Construction |
- |
LMH |
Cat2 |
325 |
88% |
329.0 |
- |
- |
17.5 |
Probable |
T |
Demand management & community programmes |
EBOP Road Safety Community Programmes |
Implementation |
|
|
App. |
432 |
75% |
- |
125.8 |
- |
- |
|
N |
EBOP Road Safety TDM Community Programmes |
Implementation |
|
App. |
432 |
75% |
- |
75.1 |
- |
- |
|
N |
Walking and cycling facilities |
Walking and Cycling - Access and community benefits |
Group allocation |
|
|
Alloc. |
|
|
|
- |
- |
- |
|
|
WDC Cycling Facilities (Minor Projects) 2009/10 |
Construction |
102 |
LMM |
Reserve |
452 |
55% |
150.0 |
82.5 |
- |
- |
Res. A |
|
WDC Cycling Facilities (Minor Projects) 2010/11 |
Construction |
102 |
LMM |
Reserve |
452 |
55% |
155.0 |
- |
85.3 |
- |
Res. A |
|
WDC Cycling Facilities (Minor Projects) 2011/12 |
Construction |
102 |
LMM |
Reserve |
452 |
55% |
160.0 |
- |
- |
88.0 |
Res. A |
|
WDC Cycling Facilities (Gorge Rd) 2009/10 |
Design |
102 |
LMM |
Reserve |
452 |
55% |
150.0 |
82.5 |
- |
- |
Res. A |
|
WDC Cycling Facilities (Gorge Rd) 2010/11 |
Construction |
102 |
LMM |
Reserve |
452 |
55% |
1,094.0 |
- |
601.7 |
- |
Res. A |
|
WDC Cycling Facilities (Ohope Rd) 2009/10 |
Construction |
102 |
LMM |
Reserve |
452 |
55% |
431.0 |
237.1 |
- |
- |
Res. A |
|
WDC Pedestrian Facilities (Minor Projects) 2009/10 |
Construction |
103 |
LMM |
Reserve |
451 |
55% |
198.0 |
108.9 |
- |
- |
Res. A |
|
WDC Pedestrian Facilities (Minor Projects) 2010/11 |
Construction |
103 |
LMM |
Reserve |
451 |
55% |
205.0 |
- |
112.8 |
- |
Res. A |
|
WDC Pedestrian Facilities (Minor Projects) 2011/12 |
Construction |
103 |
LMM |
Reserve |
451 |
55% |
211.0 |
- |
- |
116.1 |
Res. A |
|
Transport planning |
Whakatane Walking and Cycling Strategy Development 2008/09 |
Study |
- |
|
Com |
002 |
75% |
77.0 |
35.3 |
- |
- |
|
N |
WDC AMP Improvements |
Study |
80 |
ML_ |
Cat2 |
003 |
55% |
50.0 |
- |
27.5 |
- |
|
N |
WDC Crash Reduction Study 2009/10 |
Study |
65 |
MM_ |
Cat2 |
002 |
75% |
50.0 |
37.5 |
- |
- |
|
N |
WDC Matata to Nukuhou Arterial Improvement Strategy 2010/11 |
Study |
66 |
MM_ |
Cat2 |
002 |
75% |
50.0 |
- |
37.5 |
- |
|
N |
WDC Walking and Cycling Strategy Review |
Study |
- |
|
N/F |
|
|
|
|
|
|
|
|
Whakatane District Council SPR |
Renewal of local roads |
Road renewals |
SPR |
|
|
App. |
|
|
2,649.0 |
918.0 |
1,004.0 |
727.0 |
|
N |
Operation and maintenance of local roads |
Road operations and maintenance |
SPR |
|
|
App. |
|
|
1,418.0 |
454.0 |
481.0 |
483.0 |
|
N |
New & improved infrastructure for local roads |
Minor improvements 2009/12 |
SPR |
|
|
App. |
341 |
|
- |
109.8 |
105.7 |
84.9 |
|
N |