National Land Transport Programme 2009-2012

Appendix 3: Nationally delivered or managed activities

Return to Appendix 3

  Phase Regional priority Profile Status Work category Indicative FAR* Total phase cost 2009/10 NLTF ($000) 2010/11 NLTF ($000) 2011/12 NLTF ($000) Funding priority Funding source*
NZ Transport Agency
New & improved infrastructure for state highways
Toll Systems Project - Stage 1 Construction     Com 323 100% 22,814.2 2,100.0 - -   N
Unallocated               41,251.2 180,266.7 494,967.7   N/R/C
Renewal of state highways
Preventive maintenance - unallocated               7,851.3 8,017.3 8,017.3   N
Operation and maintenance of state highways
Emergency works - unallocated               18,526.5 36,982.7 37,982.7   N
New & improved infrastructure for local roads
Unallocated               13,227.0 47,956.7 71,964.4   N/R/C
Renewal of local roads
Preventive maintenance - unallocated               5,056.7 4,720.2 4,787.9   N
Operation and maintenance of local roads
Emergency works - unallocated               42,338.3 57,755.6 58,394.0   N
Public transport infrastructure
Unallocated               40,727.0 33,298.2 48,468.1   N/R/C
Public transport services
Public transport services - unallocated               3,522.2 5,254.2 6,889.3   N
Demand management & community programmes
AADEF - SADD Implementation     App. 432 100% - 315.0 - -   N
Advertising - general administration Implementation     App. 432 100% - 26.0 - -   N
Awards Programme Implementation     App. 432 100% - 177.2 - -   N
Community Resources and Guidelines Implementation     App. 432 100% - 148.1 - -   N
Cyclist Skills Training Implementation     App. 432 100% - 183.3 - -   N
Drink Driving Implementation     App. 432 100% - 3,485.1 - -   N
Fatigue Implementation     App. 432 100% - 763.5 - -   N
Foundation Certificate in Injury Prevention Implementation     App. 432 100% - 40.6 - -   N
Getting There Implementation Implementation     App. 432 100% - 171.3 - -   N
Intersection Behaviour Implementation     App. 432 100% - 3,227.6 - -   N
Maori and Pacific Implementation     App. 432 100% - 1,120.1 - -   N
#REF! Implementation     App. 432 100% - 164.5 - -   N
#REF! Implementation     App. 432 100% - 102.2 - -   N
Research and Evaluation Implementation     App. 432 100% - 1,229.4 - -   N
Right Car / Fuel Saver Implementation     App. 432 100% - 354.1 - -   N
Safe 2 Go Implementation     App. 432 100% - 116.7 - -   N
Safe with Age Implementation     App. 432 100% - 600.0 - -   N
Safety Belts Implementation     App. 432 100% - 433.8 - -   N
School Road Safety Education (Road Sense) Implementation     App. 432 100% - 1,871.7 - -   N
Speed Implementation     App. 432 100% - 3,303.1 - -   N
Strengthening User Group Networks Implementation     App. 432 100% - 940.7 - -   N
Tactical Implementation     App. 432 100% - 1,275.3 - -   N
Tracks are for Trains Implementation     App. 432 100% - 97.1 - -   N
TraffiNZ Implementation     App. 432 100% - 50.1 - -   N
Travel Planning Education (WSB, Feetfirst) Implementation     App. 432 100% - 549.8 - -   N
Vehicle Safety Implementation     App. 432 100% - 1,084.8 - -   N
Walking and Cycling Programme (Bikewise) Implementation     App. 432 100% - 479.5 - -   N
Youth and Novice Driver (Practice) Implementation     App. 432 100% - 558.4 - -   N
Early Childhood Implementation     N/F                
Networks Advice Implementation     N/F                
Locally delivered programmes - unallocated 1,338.2 16,537.3 14,582.3   N
NZTA costs - unallocated               213.1 23,082.0 23,082.0   N
Walking and cycling facilities
Unallocated               2,095.3 6,889.1 3,319.9   N/R
Transport planning
Corridor Study on Regional Customer Service needs Strategy Study     Com 002 100% 200.0 200.0 - -   N
Freight Requirements Corridor Study Study     Com 002 100% 300.0 300.0 - -   N
National Safety Corridor Startegy Development Study     Com 002 100% 300.0 300.0 - -   N
National State Highway Update Study     Com 002 100% 100.0 100.0 - -   N
Optimisation Corridor Studies Study     Com 002 100% 1,265.0 1,265.0 - -   N
Safekids - Child Restraint Campaign Implementation     App. 432 100% - 35.0 - -   N
Long Term Pavement Performance Monitoring Project       App. 003 100% 3,250.0 650.0 650.0 650.0    
Unallocated             - 13,473.0 23,104.3 23,098.6   N
Rail freight and sea freight
NZTA Central Log Rail Implementation Funding Construction     Com 441 100% 975.0 400.0 300.0 275.0    
Tangiwai to Centre Port Rail Freight Construction     Com 441 100% 820.0 250.0 350.0 220.0    
Tangiwai to Centre Port Rail Freight Construction     Com 441 100% 820.0 250.0 350.0 220.0    

Return to Appendix 3