In the 2018–21 NLTP, $112 million of Public transport projects have been approved for funding in the Canterbury district. This includes $1.7 million of funding in the latest prioritisation round for new ticketing systems and replacement of real time information. A further $5.7 million of funding is likely for the Future Public transport detailed and indicative business cases.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
Electronic Ticketing System Enhancement | Public transport capex | Implementation | Approved |
National Ticketing Projects – Project NEXT | Public transport capex | Detailed business case | Approved |
National Ticketing Projects – Project NEXT | Public transport capex | Implementation | Likely |
Real Time Information replacement | Public transport opex | Implementation | Approved |
Future PT Business Case Implementation: Stage 1 and 2 | Public transport opex | Detailed business case | Likely |
Future PT Business Case Implementation: Stage 1 and 2 | Public transport opex | Indicative business case | Likely |
In the 2018–21 NLTP, $28 million of land transport projects have been approved for funding in the Kaikōura district. This includes $5 million of funding in the latest prioritisation round for improvements to Route 70, the alternative access route to Kaikōura.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
Kaikōura Nov 2016 EQ: route 70 improvements KDC | Local road improvements | Implementation | Approved |
In the 2018–21 NLTP, $47 million of land transport projects have been approved for funding in the Hurunui district. This includes more than $5.4 million of funding in the latest prioritisation round for improvements to Route 70, the Johnston Street level crossing and replacement of street lights with LEDS.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
Johnston Street Level Crossing Improvements | Local road improvements | Construction | Approved |
Kaikōura Nov 2016 EQ: route 70 improvements HDC | Local road improvements | Implementation | Approved |
Street Lighting Renewal – LED conversion | Local road improvements | Implementation | Approved |
In the 2018–21 NLTP, $33 million of land transport projects have been approved for funding in the Waimakariri district. This includes more than $400,000 of funding in the latest prioritisation round to complete three rail level crossing upgrades and accelerate the district’s street lighting upgrades to LEDs.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
Accelerated LED Programme | Local road improvements | Implementation | Approved |
High Street Level Crossing Pedestrian Maze | Local road improvements | Construction | Approved |
Southbrook Road/South Belt Intersection Upgrade | Local road improvements | Construction | Approved |
Wales Street Rail Level Crossing Upgrade | Local road improvements | Construction | Approved |
West Kaiapoi – Mill Road to Skewbridge Road | Regional improvements | Detailed business case | *Likely |
West Kaiapoi – Mill Road to Skewbridge Road | Regional improvements | Pre-implementation | *Likely |
West Kaiapoi – Mill Road to Skewbridge Road | Regional improvements | Construction | Unlikely |
*Likely – post the May prioritisation, these projects were reviewed following additional information provided by the Waimakariri District Council and the status changed from unlikely to likely.
In the 2018–21 NLTP, $223 million of land transport projects have been approved for funding in Christchurch. This includes $14.5 million of funding in the latest prioritisation round for Local road improvements and $11.4 million of walking and cycling projects.
Another, $46.6 million of Local road improvements and walking and cycling projects have been identified as likely to receive funding during this NLTP period, if funding is available at the time a funding application is received.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
AAC Ferry Rd (St Asaph – Fitzgerald) | Local road improvements | Detailed business case | Approved |
AAC TP30k: Slow Core | Local road improvements | Construction | Approved |
AAC Victoria Street | Local road improvements | Construction | Approved |
Accelerated LED Conversion Programme | Local road improvements | Implementation | Approved |
Christchurch Northern Corridor – Local Share Activity | Local road improvements | Implementation | Approved |
Cluster 4: Moorhouse Ave: Detailed Business Case | Local road improvements | Detailed business case | Approved |
Cluster 6 – Lincoln Rd (Curletts – Wrights) T | Local road improvements | Detailed business case | Approved |
Intersection Safety: Gasson/ Madras/ Moorhouse (1) | Local road improvements | Construction | Approved |
Northern Arterial Extension and Cranford Street Upgrade | Local road improvements | Construction | Approved |
AAC Ferry Rd (St Asaph – Fitzgerald) | Local road improvements | Implementation | Likely |
AAC Salisbury Street and Kilmore Street | Local road improvements | Construction | Likely |
Accelerated LED Conversion Programme | Local road improvements | Implementation | Likely |
Cluster 6 – Lincoln Rd (Curletts – Wrights) T | Local road improvements | Implementation | Likely |
Network Management Improvements: RoNS Downstream | Local road improvements | Construction | Likely |
Northern Arterial Extension and Cranford Street Upgrade | Local road improvements | Pre-implementation | Likely |
RONS Downstream Inter Improvements: Cranford St Downstream | Local road improvements | Construction | Likely |
TEFAR – Cluster 6-Interstn safe: Barrington/Lincoln/Whiteleigh | Local road improvements | Implementation | Likely |
TEFAR – Cluster 8-Intersection safety: Ilam/Middleton/Riccarton | Local road improvements | Implementation | Likely |
TEFAR – Corridor 1-Intersn Improvement: Cashmere/Hoon Hay/Worsley | Local road improvements | Construction | Likely |
TEFAR – Corridor 2 – Inters Improvement: Lower Styx/Marshland | Local road improvements | Construction | Likely |
TEFAR – Intersection Safety: Aldwins/Buckleys/Linwood(13) | Local road improvements | Implementation | Likely |
TEFAR -Rte Improvement: Barbadoes St & Madras St (Bealey to Warri | Local road improvements | Construction | Likely |
AAC Antigua Street (St Asaph-Moorhouse) | Local road improvements | Construction | *Likely |
AAC Central City: Wayfinding | Local road improvements | Construction | Unlikely |
AAC Colombo Street (Bealey – Kilmore) | Local road improvements | Construction | *Likely |
AAC Hereford Street (Manchester-Cambridge) | Local road improvements | Construction | *Likely |
AAC High Street (Hereford-Manchester) | Local road improvements | Construction | *Likely |
AAC High Street (Manchester-St Asaph) | Local road improvements | Construction | Unlikely |
Burwood & North Shirley Rd Reconstruction | Local road improvements | Implementation | Unlikely |
Halswell Junction Road Extension: General Traffic Upgrades | Local road improvements | Construction | Unlikely |
Intersection Improvement: Burwood/Mairehau: Development Nth | Local road improvements | Construction | Unlikely |
Intersection Safety: Bealey/Papanui/Victoria (14) | Local road improvements | Construction | Unlikely |
Network Management Improvement: McLeans Island Rd & Pound Rd | Local road improvements | Implementation | Unlikely |
New Link: Halswell Junction to Connaught: Development S-W | Local road improvements | Implementation | Unlikely |
R102 Pages Road Bridge: General Traffic Upgrade | Local road improvements | Detailed business case | Unlikely |
RONS Downstream Inter Safety: Main Rd/Marshland/Spencerville | Local road improvements | Construction | *Likely |
Safety Improvements: Guardrails – Dyers Pass Rd | Local road improvements | Construction | *Likely |
CSA Bus interchange construction | Public transport capex | Construction | Approved |
Cluster 1 – PT Facilities: Northlands Hub | Public transport capex | Construction | *Likely |
Cluster 8 – PT Infrastructure to support Hubs & Spokes | Public transport capex | Construction | Unlikely |
TEFAR – Cluster 1 – Core PT Route: North (Papanui & Belfast) | Public transport capex | Construction | Unlikely |
TEFAR – Riccarton Interchange and Bus Priority | Public transport capex | Implementation | Unlikely |
Major Cycleway: Little River Link (Little River Route) UCF | Walking and cycling | Construction | Approved |
Major Cycleway: Papanui Parallel (Section 1, 2, 3 and 4) UCF | Walking and cycling | Construction | Approved |
Major Cycleway: Rapanui – Shag Rock (Sumner to City) UCF | Walking and cycling | Implementation | Approved |
Major Cycleway: Rapanui – Shag Rock (Sumner to City) UCF | Walking and cycling | Construction | Approved |
Major Cycleway: Uni-Cycle (University to City) UCF | Walking and cycling | Construction | Approved |
Major Cycleway: Uni-Cycle (University to City) UCF | Walking and cycling | Construction | Approved |
Major Cycleway: Heathcote Expressway (Heathcote Rail-City) UCF | Walking and cycling | Implementation | Approved |
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T | Walking and cycling | Construction | Approved |
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T | Walking and cycling | Construction | Approved |
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T | Walking and cycling | Construction | Approved |
Major Cycleway: Quarryman's Trail (Halswell to City) UCF T | Walking and cycling | Construction | Approved |
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T | Walking and cycling | Construction | Likely |
Major Cycleway: South Express (Hornby Rail-Templeton to City) | Walking and cycling | Construction | Likely |
Major Cycleway: South Express (Hornby Rail-Templeton to City) | Walking and cycling | Construction | Likely |
TEFAR – Major Cycleway: Nor'West Arc | Walking and cycling | Construction | Likely |
TEFAR – Major Cycleway: Nor'West Arc | Walking and cycling | Construction | Likely |
TEFAR – Major Cycleway: Nor'West Arc | Walking and cycling | Construction | Likely |
TEFAR – Major Cycleway: Nor'West Arc | Walking and cycling | Construction | Likely |
TEFAR – Major Cycleway: Southern Lights (South to City) | Walking and cycling | Construction | Likely |
Belfast Park Plan Change 43: Underpass: Development North | Walking and cycling | Implementation | Unlikely |
Coastal Pathway Project | Walking and cycling | Construction | Unlikely |
Local Cycleway: Northern Arterial Link Cranford-Rutland Reserve | Walking and cycling | Construction | Unlikely |
*Likely – post the May prioritisation, these projects were reviewed following additional information provided by the Christchurch City Council and the status changed from unlikely to likely.
In the 2018–21 NLTP, $34 million of land transport projects have been approved for funding in the Selwyn district. This includes $2.4 million of funding in the latest prioritisation round for Local road improvements: the widening of Walkers Road, the replacement of street lights with LEDs, and an indicative business case for improvements to Rolleston’s town centre. Funding has also been approved for the construction of the Lincoln-Rolleston Cycleway.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
LED Upgrade | Local road improvements | Implementation | Approved |
Rolleston Town Centre – Town of the Future | Local road improvements | Indicative business case | Approved |
Walkers Road Widening | Local road improvements | Implementation | Approved |
Prebbleton Arterial CSM Related Upgrade Packages | Local road improvements | Implementation | Unlikely |
Prebbleton Arterial CSM Related Upgrade Packages – Springs Marsh intersection | Local road improvements | Implementation | *Likely |
Prebbleton Arterial CSM Related Upgrade Packages – Shands/Blakes intersection | Local road improvements | Implementation | *Likely |
Selwyn Coordinated Transport Upgrades | Local road improvements | Implementation | Unlikely |
Lincoln Rolleston Cyclway | Walking and cycling | Construction | Approved |
Lincoln Rolleston Cyclway | Walking and cycling | Construction | Approved |
Selwyn Coordinated Transport Upgrades – Rolleston to Templeton Cycleway | Walking and cycling | Implementation | Unlikely |
*Likely – post the May prioritisation, these projects were reviewed following additional information provided by the Selwyn District Council and the status changed from unlikely to likely.
In the 2018–21 NLTP, $33 million of land transport projects have been approved for funding in Ashburton. This includes $1.3 million of funding in the latest prioritisation round to complete a detailed business case for a second urban bridge over the Ashburton River and to accelerate the renewal of street lighting with LEDs.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
ADC Accelerated renewal road lighting LED conversion | Local road improvements | Implementation | Approved |
Second Ashburton Urban Bridge, Ashburton River | Local road improvements | Detailed business case | Approved |
In the 2018–21 NLTP, $9 million of land transport projects have been approved for funding in the Mackenzie district. This includes more than $675,000 of funding in the latest prioritisation round to accelerate the replacement of street lighting throughout the district with LEDs.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
LED Street Lighting accelerated renewals | Local road improvements | Construction | Approved |
Lilybank Road Seal Extension | Regional improvements | Indicative business case | Unlikely |
Lilybank Road Seal Extension | Regional improvements | Indicative business case | Unlikely |
In the 2018–21 NLTP, $36 million of land transport projects have been approved for funding in the Timaru district. This includes more than $33,000 of funding in the latest prioritisation round to accelerate the replacement of street lighting throughout the district with LEDs.
It is also likely that $765,000 will be available to complete upgrades at the Washdyke industrial area.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
LED Street Lighting accelerated renewals | Local road improvements | Construction | Approved |
Washdyke Industrial area road upgrades | Regional improvements | Construction | Likely |
Timaru Port Southern Access | Regional improvements | Pre-implementation | Unlikely |
In the 2018–21 NLTP, $12 million of land transport projects have been approved for funding in the Waimate district. This includes more than $21,000 of funding in the latest prioritisation round to accelerate the replacement of street lighting throughout the district with LEDs.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
Accelerated LED Street Light Renewal | Local road improvements | Implementation | Approved |
In the 2018–21 NLTP, $26 million of land transport projects have been approved for funding in the Waitaki district. This includes $563,000 of funding in the latest prioritisation round to upgrade street lighting to LEDs and complete improvements to the Waitaki Avenue level crossing.
Project name | Activity class | Phase | Approved/Likely/ Unlikely to be funded |
---|---|---|---|
Streetlight LED upgrade 2016-2018 | Local road improvements | Construction | Approved |
Waitaki Avenue level crossing upgrade | Local road improvements | Construction | Approved |
Kakanui Point Bridge Business Case Development | Regional improvements | Detailed business case | Unlikely |
Kakanui Point Bridge Design & Construction 2019–21 | Regional improvements | Pre-implementation | Unlikely |
Kakanui Point Bridge Design & Construction 2019-21 | Regional improvements | Construction | Unlikely |