In the 2018–21 NLTP, $112 million of Public transport projects have been approved for funding in the Canterbury district. This includes $1.7 million of funding in the latest prioritisation round for new ticketing systems and replacement of real time information. A further $5.7 million of funding is likely for the Future Public transport detailed and indicative business cases.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
Electronic Ticketing System Enhancement Public transport capex Implementation Approved
National Ticketing Projects – Project NEXT Public transport capex Detailed business case Approved
National Ticketing Projects – Project NEXT Public transport capex Implementation Likely
Real Time Information replacement Public transport opex Implementation Approved
Future PT Business Case Implementation: Stage 1 and 2 Public transport opex Detailed business case Likely
Future PT Business Case Implementation: Stage 1 and 2 Public transport opex Indicative business case Likely

Kaikōura District Council

In the 2018–21 NLTP, $28 million of land transport projects have been approved for funding in the Kaikōura district. This includes $5 million of funding in the latest prioritisation round for improvements to Route 70, the alternative access route to Kaikōura.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
Kaikōura Nov 2016 EQ: route 70 improvements KDC Local road improvements Implementation Approved

Hurunui District Council

In the 2018–21 NLTP, $47 million of land transport projects have been approved for funding in the Hurunui district. This includes more than $5.4 million of funding in the latest prioritisation round for improvements to Route 70, the Johnston Street level crossing and replacement of street lights with LEDS.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
Johnston Street Level Crossing Improvements Local road improvements Construction Approved
Kaikōura Nov 2016 EQ: route 70 improvements HDC Local road improvements Implementation Approved
Street Lighting Renewal – LED conversion Local road improvements Implementation Approved

Waimakariri District Council

In the 2018–21 NLTP, $33 million of land transport projects have been approved for funding in the Waimakariri district. This includes more than $400,000 of funding in the latest prioritisation round to complete three rail level crossing upgrades and accelerate the district’s street lighting upgrades to LEDs.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
Accelerated LED Programme Local road improvements Implementation Approved
High Street Level Crossing Pedestrian Maze Local road improvements Construction Approved
Southbrook Road/South Belt Intersection Upgrade Local road improvements Construction Approved
Wales Street Rail Level Crossing Upgrade Local road improvements Construction Approved
West Kaiapoi – Mill Road to Skewbridge Road Regional improvements Detailed business case *Likely
West Kaiapoi – Mill Road to Skewbridge Road Regional improvements Pre-implementation *Likely
West Kaiapoi – Mill Road to Skewbridge Road Regional improvements Construction Unlikely

*Likely – post the May prioritisation, these projects were reviewed following additional information provided by the Waimakariri District Council and the status changed from unlikely to likely.

Christchurch City Council

In the 2018–21 NLTP, $223 million of land transport projects have been approved for funding in Christchurch. This includes $14.5 million of funding in the latest prioritisation round for Local road improvements and $11.4 million of walking and cycling projects.

Another, $46.6 million of Local road improvements and walking and cycling projects have been identified as likely to receive funding during this NLTP period, if funding is available at the time a funding application is received.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
AAC Ferry Rd (St Asaph – Fitzgerald) Local road improvements Detailed business case Approved
AAC TP30k: Slow Core Local road improvements Construction Approved
AAC Victoria Street Local road improvements Construction Approved
Accelerated LED Conversion Programme Local road improvements Implementation Approved
Christchurch Northern Corridor – Local Share Activity Local road improvements Implementation Approved
Cluster 4: Moorhouse Ave: Detailed Business Case Local road improvements Detailed business case Approved
Cluster 6 – Lincoln Rd (Curletts – Wrights) T Local road improvements Detailed business case Approved
Intersection Safety: Gasson/ Madras/ Moorhouse (1) Local road improvements Construction Approved
Northern Arterial Extension and Cranford Street Upgrade Local road improvements Construction Approved
AAC Ferry Rd (St Asaph – Fitzgerald) Local road improvements Implementation Likely
AAC Salisbury Street and Kilmore Street Local road improvements Construction Likely
Accelerated LED Conversion Programme Local road improvements Implementation Likely
Cluster 6 – Lincoln Rd (Curletts – Wrights) T Local road improvements Implementation Likely
Network Management Improvements: RoNS Downstream Local road improvements Construction Likely
Northern Arterial Extension and Cranford Street Upgrade Local road improvements Pre-implementation Likely
RONS Downstream Inter Improvements: Cranford St Downstream Local road improvements Construction Likely
TEFAR – Cluster 6-Interstn safe: Barrington/Lincoln/Whiteleigh Local road improvements Implementation Likely
TEFAR – Cluster 8-Intersection safety: Ilam/Middleton/Riccarton Local road improvements Implementation Likely
TEFAR – Corridor 1-Intersn Improvement: Cashmere/Hoon Hay/Worsley Local road improvements Construction Likely
TEFAR – Corridor 2 – Inters Improvement: Lower Styx/Marshland Local road improvements Construction Likely
TEFAR – Intersection Safety: Aldwins/Buckleys/Linwood(13) Local road improvements Implementation Likely
TEFAR -Rte Improvement: Barbadoes St & Madras St (Bealey to Warri Local road improvements Construction Likely
AAC Antigua Street (St Asaph-Moorhouse) Local road improvements Construction *Likely
AAC Central City: Wayfinding Local road improvements Construction Unlikely
AAC Colombo Street (Bealey – Kilmore) Local road improvements Construction *Likely
AAC Hereford Street (Manchester-Cambridge) Local road improvements Construction *Likely
AAC High Street (Hereford-Manchester) Local road improvements Construction *Likely
AAC High Street (Manchester-St Asaph) Local road improvements Construction Unlikely
Burwood & North Shirley Rd Reconstruction Local road improvements Implementation Unlikely
Halswell Junction Road Extension: General Traffic Upgrades Local road improvements Construction Unlikely
Intersection Improvement: Burwood/Mairehau: Development Nth Local road improvements Construction Unlikely
Intersection Safety: Bealey/Papanui/Victoria (14) Local road improvements Construction Unlikely
Network Management Improvement: McLeans Island Rd & Pound Rd Local road improvements Implementation Unlikely
New Link: Halswell Junction to Connaught: Development S-W Local road improvements Implementation Unlikely
R102 Pages Road Bridge: General Traffic Upgrade Local road improvements Detailed business case Unlikely
RONS Downstream Inter Safety: Main Rd/Marshland/Spencerville Local road improvements Construction *Likely
Safety Improvements: Guardrails – Dyers Pass Rd Local road improvements Construction *Likely
CSA Bus interchange construction Public transport capex Construction Approved
Cluster 1 – PT Facilities: Northlands Hub Public transport capex Construction *Likely
Cluster 8 – PT Infrastructure to support Hubs & Spokes Public transport capex Construction Unlikely
TEFAR – Cluster 1 – Core PT Route: North (Papanui & Belfast) Public transport capex Construction Unlikely
TEFAR – Riccarton Interchange and Bus Priority Public transport capex Implementation Unlikely
Major Cycleway: Little River Link (Little River Route) UCF Walking and cycling Construction Approved
Major Cycleway: Papanui Parallel (Section 1, 2, 3 and 4) UCF Walking and cycling Construction Approved
Major Cycleway: Rapanui – Shag Rock (Sumner to City) UCF Walking and cycling Implementation Approved
Major Cycleway: Rapanui – Shag Rock (Sumner to City) UCF Walking and cycling Construction Approved
Major Cycleway: Uni-Cycle (University to City) UCF Walking and cycling Construction Approved
Major Cycleway: Uni-Cycle (University to City) UCF Walking and cycling Construction Approved
Major Cycleway: Heathcote Expressway (Heathcote Rail-City) UCF Walking and cycling Implementation Approved
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T Walking and cycling Construction Approved
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T Walking and cycling Construction Approved
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T Walking and cycling Construction Approved
Major Cycleway: Quarryman's Trail (Halswell to City) UCF T Walking and cycling Construction Approved
Major Cycleway: Northern Line (Northern Rail Route to Riccarton) UCF T Walking and cycling Construction Likely
Major Cycleway: South Express (Hornby Rail-Templeton to City) Walking and cycling Construction Likely
Major Cycleway: South Express (Hornby Rail-Templeton to City) Walking and cycling Construction Likely
TEFAR – Major Cycleway: Nor'West Arc Walking and cycling Construction Likely
TEFAR – Major Cycleway: Nor'West Arc Walking and cycling Construction Likely
TEFAR – Major Cycleway: Nor'West Arc Walking and cycling Construction Likely
TEFAR – Major Cycleway: Nor'West Arc Walking and cycling Construction Likely
TEFAR – Major Cycleway: Southern Lights (South to City) Walking and cycling Construction Likely
Belfast Park Plan Change 43: Underpass: Development North Walking and cycling Implementation Unlikely
Coastal Pathway Project Walking and cycling Construction Unlikely
Local Cycleway: Northern Arterial Link Cranford-Rutland Reserve Walking and cycling Construction Unlikely

*Likely – post the May prioritisation, these projects were reviewed following additional information provided by the Christchurch City Council and the status changed from unlikely to likely.

Selwyn District Council

In the 2018–21 NLTP, $34 million of land transport projects have been approved for funding in the Selwyn district. This includes $2.4 million of funding in the latest prioritisation round for Local road improvements: the widening of Walkers Road, the replacement of street lights with LEDs, and an indicative business case for improvements to Rolleston’s town centre. Funding has also been approved for the construction of the Lincoln-Rolleston Cycleway.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
LED Upgrade Local road improvements Implementation Approved
Rolleston Town Centre – Town of the Future Local road improvements Indicative business case Approved
Walkers Road Widening Local road improvements Implementation Approved
Prebbleton Arterial CSM Related Upgrade Packages Local road improvements Implementation Unlikely
Prebbleton Arterial CSM Related Upgrade Packages – Springs Marsh intersection Local road improvements Implementation *Likely
Prebbleton Arterial CSM Related Upgrade Packages – Shands/Blakes intersection Local road improvements Implementation *Likely
Selwyn Coordinated Transport Upgrades Local road improvements Implementation Unlikely
Lincoln Rolleston Cyclway Walking and cycling Construction Approved
Lincoln Rolleston Cyclway Walking and cycling Construction Approved
Selwyn Coordinated Transport Upgrades – Rolleston to Templeton Cycleway Walking and cycling Implementation Unlikely

*Likely – post the May prioritisation, these projects were reviewed following additional information provided by the Selwyn District Council and the status changed from unlikely to likely.

Ashburton District Council

In the 2018–21 NLTP, $33 million of land transport projects have been approved for funding in Ashburton. This includes $1.3 million of funding in the latest prioritisation round to complete a detailed business case for a second urban bridge over the Ashburton River and to accelerate the renewal of street lighting with LEDs.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
ADC Accelerated renewal road lighting LED conversion Local road improvements Implementation Approved
Second Ashburton Urban Bridge, Ashburton River Local road improvements Detailed business case Approved

Mackenzie District Council

In the 2018–21 NLTP, $9 million of land transport projects have been approved for funding in the Mackenzie district. This includes more than $675,000 of funding in the latest prioritisation round to accelerate the replacement of street lighting throughout the district with LEDs.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
LED Street Lighting accelerated renewals Local road improvements Construction Approved
Lilybank Road Seal Extension Regional improvements Indicative business case Unlikely
Lilybank Road Seal Extension Regional improvements Indicative business case Unlikely

Timaru District Council

In the 2018–21 NLTP, $36 million of land transport projects have been approved for funding in the Timaru district. This includes more than $33,000 of funding in the latest prioritisation round to accelerate the replacement of street lighting throughout the district with LEDs.

It is also likely that $765,000 will be available to complete upgrades at the Washdyke industrial area.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
LED Street Lighting accelerated renewals Local road improvements Construction Approved
Washdyke Industrial area road upgrades Regional improvements Construction Likely
Timaru Port Southern Access Regional improvements Pre-implementation Unlikely

Waimate District Council

In the 2018–21 NLTP, $12 million of land transport projects have been approved for funding in the Waimate district. This includes more than $21,000 of funding in the latest prioritisation round to accelerate the replacement of street lighting throughout the district with LEDs.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
Accelerated LED Street Light Renewal Local road improvements Implementation Approved

Waitaki District Council

In the 2018–21 NLTP, $26 million of land transport projects have been approved for funding in the Waitaki district. This includes $563,000 of funding in the latest prioritisation round to upgrade street lighting to LEDs and complete improvements to the Waitaki Avenue level crossing.

Project name Activity class Phase Approved/Likely/
Unlikely to be funded
Streetlight LED upgrade 2016-2018 Local road improvements Construction Approved
Waitaki Avenue level crossing upgrade Local road improvements Construction Approved
Kakanui Point Bridge Business Case Development Regional improvements Detailed business case Unlikely
Kakanui Point Bridge Design & Construction 2019–21 Regional improvements Pre-implementation Unlikely
Kakanui Point Bridge Design & Construction 2019-21 Regional improvements Construction Unlikely