A stretch of State Highway 3 around the Mangorei Road roundabout construction site will be under night-time stop/go traffic management from next week as crews rebuild the road surface.
Work will begin on Sunday night (30 March) and is expected to take 3 weeks to complete.
Crews will be working 5 nights per week, from 6pm to 6am Sunday to Thursday (wrapping up each week at 6am Friday) for each of the 3 weeks.
Those needing to travel to or from property within the site should speak with one of the onsite crew members for assistance.
SH3 access to and from Mangorei Road will be closed during the night works. Alternative routes to Mangorei Road are available via Carrington and Baker Roads, as well as via Cumberland Street.
Outside of the night works, access to and from Mangorei Road will be restored and the SH3 stop/go will be lifted.
Users of SH3 will have seen work progressing on the construction of the roundabout and associated improvements at the Mangorei Road intersection.
Since construction began last November, contractors have carried out a wide variety of works, while working to minimise disruption for local residents and those travelling through the intersection.
To date the works have included:
Work over the coming 2-3 months will include:
Crews will begin the work next Monday (31 March), focussing initially on a section of SH3 south of the intersection with Waitara Road.
To complete this rebuild safely and efficiently, this section of SH3 will be closed at nights, from 8pm to 5.30am, Monday to Friday. During the day it will remain open under a temporary speed limit.