Regular users of State Highway 6 between Rai Valley and Hira need to be ready for three weeks of night closures starting next week.
Resurfacing and maintenance work is scheduled for the Whangamoa Saddle from 23 February until 13 March.
During this time State Highway 6 between Hira and Rai Valley will be closed from 8 pm to 5.30 am, Sunday to Thursday nights. No work will be done on Friday and Saturdays.
To take advantage of this closure and reduce disruption on the route, the Pelorus Bridge on State Highway 6 between Havelock and Rai Valley will also be closed on the night of 23 February from 8 pm until 5.30 am to allow one of its deck panels to be replaced. The bridge will be open for traffic at 12:30 am.
Road crews will be carrying out road resurfacing and other essential maintenance work including
clearing drains, replacing a culvert, completing resilience improvements, and other general works.
All the work has been deliberately timed to happen at night and outside peak summer holiday traffic to ensure it affects as few road users as possible.
Full closures are being used because of narrowness of the road and the equipment being used. It is not feasible or safe for road users or workers to run stop/go traffic management. The closures will allow the work to be completed faster and with lower traffic management costs.
The highway will be opened once per night at 12:30 am to let traffic through. Road users, particularly freight operators are urged to plan carefully to ensure they meet this schedule.
Drivers also need to be aware of other state highway maintenance work planned for the region in February and March, and to check road conditions before they travel.
Other State Highway maintenance works:
SH6 Whangamoa Saddle - works schedule and location:
SH6 Pelorus Bridge - works schedule and location:
Detour Route:
Works Location: