Nelson drivers must be ready as the next stage of safety improvement works on State Highway 6 Whakatu Drive in Nelson begins this weekend.
Contactors are installing safety barriers below overbridges along Whakatu Drive to help protect road users and the bridge structures in the event of a crash.
Stage two of these works begins this Sunday, 17 March, and continues until 27 March. It will require night closures of the route between the Annesbrook Roundabout and Link Road/Raeward Roundabout between 8:30 pm and 5:30 am.
The closures are essential to ensure the safety of work crews. They will also allow the construction to be completed much faster.
Every effort is being made to minimise disruption for drivers, so the closures have been timed to happen at night when there is less traffic on the road.
However, the closure means drivers will have to use local road detours via Main Road Stoke, which will mean longer journey times and road users must factor this into their travel plans.
The highway will be fully open on Friday and Saturday nights, as contractors will not be working on these nights.
Work Programme:
Stage |
Impact on SH6 Whakatu Drive |
Work being carried out |
STAGE 1 Sunday, 18 February to Sunday, 17 March |
OPEN BOTH DIRECTIONS
|
|
STAGE 2 Sunday, 17 March to Wednesday, 27 March |
NIGHT CLOSURES
Traffic management and a temporary speed limit will be in place.
|
|
STAGE 3 Wednesday, 27 March to Tuesday 16 April |
OPEN BOTH DIRECTIONS
|
|
Please note that traffic management and a reduced temporary speed limit will remain in place over the Easter weekend – Friday, 29 March to Monday, 1 April.
Works maps:
Detour route during night closures: